Pune/Project record

MahaRERA · the public record

ARYAN LANDMARK

Pune · SURAJ BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005459

Delivery and registration

When is the project declared for completion?

ARYAN LANDMARK is registered with MahaRERA as P52100005459 and the promoter has declared completion for 30 Jul 2023.

30 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005459
Registered on11 Aug 2017
Promoter-declared completion30 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ARYAN LANDMARK record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Suraj Builders is the promoter of record on 54 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

54projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ARYAN LANDMARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
A BUILDING1G+631 Jul 2019
B BUILDING1G+531 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jul 2020Project extension date wrongly estimated and now need to be revised. As we had already completed 70% work and now estimate to complete in next 8 months. Hence we are seeking 1 year
30 Jul 202030 Jan 2023EXTENSION DUE TO COVID. MOST OF THE PROJECT IS COMPLETED.

Location, Land & Connectivity

Located at Haveli, Pune, 411062. Per the filed land record, the plot is bounded to the north by GAT NO 665 PART, to the south by GAT 666 PART, to the east by GAT NO 660 and to the west by GAT NO 665 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~109 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park109 km
Baner–Balewadi belt115 km
Pune Junction / city centre125 km
Pune Int'l Airport (Lohegaon)127 km
Kharadi / EON IT Park130 km
Magarpatta / Hadapsar IT131 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Suraj Builders is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Chikhali

Elite 28
possession by Sep 2026 · Anita Mahadev Giri
Parshwa Solitaire
possession by Sep 2026 · Parshwa Realtors
Swaroop Homes
Not filing quarterly progress reports · possession by Nov 2026 · Swaroop Homes LLP
North East Business Centre
possession by Nov 2026 · Shiv Properties
Vijay Residency
possession by Dec 2026 · Rudra Infra
Akashvedh Phase 2
possession by Dec 2026 · Raghvendra Buildcon

Other RERA-registered projects in Pune

Aryan Square
declared completion Dec 2025 · M/s Krupasindhu Associates LLP
Asamant Residency
possession by Dec 2026 · Roofone CD Asamant Buildcon LLP
Aseem
declared completion Dec 2023 · Ranade Realtors LLP
Asha Paradise
declared completion Jul 2026 · G T Buildcon
Asha Park
possession by Nov 2029 · Shri Laxmi Narayan Properties LLP
Ashanand Residency Building D And E
declared completion Jun 2026 · Anand Deoram Tambe

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026