Avaunce Building F and G Phase 3

NIBM Road · Golden Palm Infrastructure

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100033303

Delivery and registration

When is the project declared for completion?

Avaunce Building F and G Phase 3 is registered with MahaRERA as P52100033303 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100033303
Registered on15 Feb 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Avaunce Building F and G Phase 3 record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Golden Palm Infrastructure is the promoter of record on 60 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

60projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Avaunce Building F and G Phase 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Avaunce Building F1G+731 Dec 2023
Avaunce Building G1G+731 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NIBM Road, NIBM Road, Pune City, Pune, 411048. Per the filed land record, the plot is bounded to the north by Gangan Builder Land, to the south by shalinitai Bhudivant land, to the east by Nala and to the west by Survey No 30. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Khurd

Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kapital
possession by Dec 2026 · Ostwal Realty
Akshardham Phase 2
possession by Dec 2026 · Shreyan Ventures
Clover Highlands
possession by Dec 2026 · Clover Developers Pvt Ltd
Hagawane Landmark
Not filing quarterly progress reports · possession by Dec 2026 · Santosh Subhash Hagawane

Major developers building in Kondhwa Khurd

Other RERA-registered projects in Pune

Avdhoot Plaza
possession by Dec 2027 · Vighnaharta Group
Avdhoot Residency
declared completion Oct 2022 · Avdhoot Constructions
Aventis
possession by Jun 2030 · Devsia Infracon LLP
Aventis - Tower A
possession by May 2031 · Devsia Infracon LLP
Aventis - Tower C & D
possession by May 2031 · Devsia Infracon LLP
Avenue 7
possession by Dec 2028 · Not Available

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.