MahaRERA Property Intelligence · Pune

BALAJI ENCLAVE

P52100017228 · KATRAJ · promoter Rushab Ravindra Dugad

Certificate SignedDue 31 Jan 2021

Delivery & Registration

MahaRERA registrationP52100017228
Registered on24 Jul 2018
Promoter-declared completion31 Jan 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rushab Ravindra Dugad is the promoter of record on 90 projects, of which 19 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BALAJI ENCLAVE1G+431 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KATRAJ, KATRAJ ROAD, Pune City, Pune, 411046. Per the filed land record, the plot is bounded to the north by DATTANAGAR ROAD, to the south by LAND OUT OF SURVEY NO 72, to the east by PROPERTY OF MR RAJKUMAR SHETE and to the west by LAND OUT OF SURVEY NO 72. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Katraj

Aishwarya Heights
possession by Jul 2026 · Shree Sadguru Construction
Basil Chandrakant
possession by Jul 2026 · Shree Sadguru Developers
Vastushree Phase-1
possession by Aug 2026 · Vastu Construction
Capella
possession by Aug 2026 · D K Realties
Divya Elite
possession by Aug 2026 · RRS Infracon LLP
Yogamrut
Not filing quarterly progress reports · possession by Aug 2026 · Jay Ganesh Buildcon

Major developers building in Katraj

Other RERA-registered projects in Pune

Balaji Heights
declared completion Nov 2022 · Concept Townships & Estate Developer
Balaji Heights
declared completion Dec 2022 · Yuvraj Landmark
Balaji Icon
possession by Dec 2027 · Yashodeep Properties
Balaji Infinity
declared completion Dec 2018 · Balaji Infinity
Balaji Krupa
possession by Jul 2026 · Santosh Dinkar Narvekar
Balaji Krupa
declared completion Mar 2025 · Shubharambh Balaji Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026