MahaRERA · the public record
Astonia Royale Phase III - P Building
Ambegaon Bk · AMIT ENTERPRISES HOUSING LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Oct 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100001045
Delivery and registration
When is the project declared for completion?
Astonia Royale Phase III - P Building is registered with MahaRERA as P52100001045 and the promoter has declared completion for 31 Oct 2026.
31 Oct 2026
declared completion
1months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100001045 |
| Registered on | 25 Jul 2017 |
| Promoter-declared completion | 31 Oct 2026 |
| Current status | Certificate Signed |
| Against today | 1 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Astonia Royale Phase III - P Building record 36 quarterly progress reports since registration.
36quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 36 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Amit Enterprises Housing is the promoter of record on 114 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
114projects
registered with MahaRERA
15flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In Astonia Royale Phase III - P Building, ₹32.30 Cr of a declared ₹41.34 Cr estimated project cost is reported as incurred, about 78.1%, as at the last certified filing with MahaRERA.
78.1%
₹32.30 Cr
of ₹41.34 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Astonia Royale Phase III - P Building, 73 of 81 homes filed with MahaRERA are recorded as sold or booked (71 with registered agreements and 2 booked), about 90%, and 8 remain available.
90%sold
73 of 81 homes
₹57.93 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹52.58 Cr (about 91%) is recorded as collected and ₹11.33 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 73 registered agreements, the effective carpet rate is ₹8,762/sqft, with eight in ten falling between ₹8,226 and ₹12,331 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.
| Floor | Unit | Carpet | Govt reckoner value |
|---|---|---|---|
| Floor 10 | 1001 | 847 sqft (78.7 sqm) | ₹65.89 Lakh |
| Floor 17 | 1702 | 844 sqft (78.39 sqm) | ₹65.08 Lakh |
| Floor 19 | 1901 | 844 sqft (78.39 sqm) | ₹65.08 Lakh |
| Floor 2 | 204 | 839 sqft (77.9 sqm) | ₹66.17 Lakh |
| Floor 21 | 2101 | 844 sqft (78.39 sqm) | ₹65.08 Lakh |
| Floor 21 | 2102 | 844 sqft (78.39 sqm) | ₹65.08 Lakh |
| Floor 21 | 2104 | 835 sqft (77.6 sqm) | ₹66.36 Lakh |
| Floor 5 | 503 | 835 sqft (77.6 sqm) | ₹66.36 Lakh |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 13 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 73 homes carry one, and 8 of the 81 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 503 | 835 sqft | Rs 74.00 lakh typical, over Rs 66.97 lakh to Rs 1.1100 cr | 20 filed on this stack, floors 1–21 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Astonia Royale Phase III - P Building, every one of the 8 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24 and 81 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Building P | 1 | G+24 | 81 | - |
Unit mix on the filing: 81 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Legal & Litigation
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| District And Session Court Pune | 112 | 2016 | Argument |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Dec 2022 | Acute economic crisis in the real estate market. |
| 30 Dec 2022 | 31 Dec 2025 | We encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector |
| 31 Dec 2025 | 30 Jun 2026 | 1. the project stands at 70% completion 2.The consent of 56.06% of allottees has been uploaded in support of this extension application. 3. PERT for the remaining completion work |
| 30 Jun 2026 | 31 Oct 2026 | 1. The project stands at 80% completion. 2. Form B uploaded. 3. PERT for the remaining completion work is uploaded in the Application. 4. The Project got delayed due to following r |
Location, Land & Connectivity
Located at Ambegaon Bk, Katraj Highway, Pune City, Pune, 411046. Per the filed land record, the plot is bounded to the north by Recreational open space, to the south by Gas Bank , to the east by Q Building and to the west by Subsequent phase O Building . These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Pune Junction / city centre | 10 km |
| Magarpatta / Hadapsar IT | 12 km |
| Baner–Balewadi belt | 13 km |
| Kharadi / EON IT Park | 16 km |
| Pune Int'l Airport (Lohegaon) | 17 km |
| Hinjewadi Rajiv Gandhi IT Park | 19 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.