Pune/Project record

MahaRERA · the public record

AMITs COLORI Phase-III G Building

Undri · AMIT ENTERPRISES HOUSING LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Mar 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100000785

Delivery and registration

When is the project declared for completion?

AMITs COLORI Phase-III G Building is registered with MahaRERA as P52100000785 and the promoter has declared completion for 28 Mar 2025.

28 Mar 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100000785
Registered on23 Jul 2017
Promoter-declared completion28 Mar 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AMITs COLORI Phase-III G Building record 31 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 31 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Amit Enterprises Housing is the promoter of record on 114 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

114projects

registered with MahaRERA

15flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AMITs COLORI Phase-III G Building in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Building G1G+13-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for AMITs COLORI Phase-III G Building, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000017780916/11/2022HEERALAL RUPARAM SUTHAR vs TATA CAPITAL HOUSING FINANCE LIMITEDorder passed
CC00500000019800228/12/2022Prajakta Sahebrao Bhosale vs Sanjeev Pateorder passed
CC00500000037092920/06/2024PAPPU MARUTI GADADE vs AMIT ENTERPRISES HOUSING LTD Throw Its Director SANJEEV GOVIND PATE, KISHOR GOVIND PATEorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Divisional Jt Registrar Pune Division Pune492017Hearing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Due to Covid19 pandemic shortage of manpower and material. Slow market condition.
30 Jun 202230 Dec 2023The construction of the said project is almost completed (approx 85%) and we need another extension to finish the remaining work and handover the units to allottees. The consent of
30 Dec 202331 Dec 2024We encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector
31 Dec 202428 Mar 20251. OC Received from Pune Municipal Corporation vide no OCC/1522/24 2. ⁠Seeking the extension till the date of OC 3. OC has uploaded in Main Application 4. Revised Form B uploade

Location, Land & Connectivity

Located at Undri, Undri Road, Pune City, Pune, 411060. Per the filed land record, the plot is bounded to the north by By Adj S N 60-2-1, to the south by By Adj S N 60-2-2 Part, to the east by By Building H and I and to the west by By Building F. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT6 km
Pune Junction / city centre9 km
Kharadi / EON IT Park11 km
Pune Int'l Airport (Lohegaon)14 km
Baner–Balewadi belt18 km
Hinjewadi Rajiv Gandhi IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Amit Enterprises Housing Limited is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Amit Enterprises Housing Limited

Amit Enterprises Housing Limited
FlaggedPune
Amit Enterprises Housing Limited
FlaggedPune
Amit Enterprises Housing Limited
FlaggedPune
Amit Enterprises Housing Limited
FlaggedPune
Amit Enterprises Housing Limited
FlaggedPune

Other RERA-registered projects in Undri

Arnav Sokande Patil Plaza
possession by Nov 2026 · Sokande Patil Prom & Developers
Raheja Sterling - Tower 3
possession by Nov 2026 · Cavalcade Properties PVT LTD
ARV Regalia
possession by Dec 2026 · Unitree India Realty LLP
Ganga Estoria C
Not filing quarterly progress reports · possession by Dec 2026 · Meenamani Real Venture LLP
Ganga Fernhill Phase 02
possession by Dec 2026 · Meenamani Ganga Builders LLP
Sukhwani Verde
possession by Dec 2026 · Sagar Gurmukh Sukhwani

Major developers building in Undri

Other RERA-registered projects in Pune

Ammons Eminent Wing B
declared completion Dec 2021 · United Constructions
Amod Vihar Apartments Condominium
possession by Dec 2028 · Dream Forge Infra Private Limited
Amoda Reserve - South Park
possession by Dec 2026 · Kalpataru Properties Private Limited
Amora Tower
declared completion Aug 2026 · Amarnath Creativity
Amorapolis Phase 4
declared completion Dec 2024 · Krisna Nirmaan Skyscraper LLP
Amrut Bliss
possession by Dec 2027 · Dashmesh Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026