MahaRERA Property Intelligence · Pune

GANGA MILLENNIA UNDRI BUILDING J AND K

P52100025499 · UNDRI · promoter Goel Ganga India

Certificate SignedDue 30 Jun 2025

Delivery & Registration

MahaRERA registrationP52100025499
Registered on08 Jun 2020
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Goel Ganga India is the promoter of record on 89 projects, of which 19 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
BUILDING J 1-10 FLOORS1G+1031 Dec 2024
BUILDING J -11-14 FLOORS1G+331 Dec 2024
BUILDING K 1-14 FLOORS1G+1431 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 8 court cases on this project to MahaRERA. 8 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Pune6662013Pending
Civil Court Pune3612015Pending
Civil Court Pune642013Pending
Civil Court Pune6992014Pending
Civil Court Pune3572015Pending
Civil Court Pune19012015Pending
Civil Court Pune11572019Pending
Civil Court Pune322016Pending

Location, Land & Connectivity

Located at UNDRI , KADNAGAR , Pune City, Pune, 411060. Per the filed land record, the plot is bounded to the north by SR NO 16 AND 17 P, to the south by 12 M WIDE ROAD, to the east by 12 M WIDE ROAD and to the west by 24 M WIDE PROPOSED ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Goel Ganga India PVT LTD is the promoter on 6 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Goel Ganga India PVT LTD project & its RERA track record →

Other flagged projects by Goel Ganga India PVT LTD

Goel Ganga India PVT LTD
Deregistered by MahaRERAPune
Goel Ganga India PVT LTD
FlaggedPune
Goel Ganga India PVT LTD
Deregistered by MahaRERAPune
Goel Ganga India PVT LTD
Deregistered by MahaRERAPune
Goel Ganga India PVT LTD
Deregistered by MahaRERAPune

Other RERA-registered projects in Undri

Lodha Pune Nibm Project
possession by Jul 2026 · Lodha Developers Limited
Samarth Rise
possession by Aug 2026 · Shri Samarth Developers
Fortune Prima
possession by Sep 2026 · Satish Shivlal Kokate
Arnav Sokande Patil Plaza
possession by Nov 2026 · Sokande Patil Prom & Developers
Raheja Sterling - Tower 3
possession by Nov 2026 · Cavalcade Properties PVT LTD
ARV Regalia
possession by Dec 2026 · Unitree India Realty LLP

Major developers building in Undri

Other RERA-registered projects in Pune

Ganga Millennia Undri Building J,k,l,m AND N
possession by Dec 2027 · Millennia Schemes Private Limited
Ganga Nakshatra
possession by Dec 2028 · Mahanagar Realty
Ganga Newtown Ph 02
declared completion Dec 2025 · Shree Balaji Associates Pune LLP
Ganga Newtown PH 3 C Bldg
declared completion Jun 2026 · Shree Balaji Associates Pune LLP
Ganga Newtown PH 4 D Bldg
possession by Dec 2027 · Shree Balaji Associates Pune LLP
Ganga Newtown PH 5 E Bldg
possession by Jun 2028 · Shree Balaji Associates Pune LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026