BALKRISHNA RESIDENCY 2

KONDHWA BK · BALKRISHNA ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 17 September 2026
30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100024906

Delivery and registration

When is the project declared for completion?

BALKRISHNA RESIDENCY 2 is registered with MahaRERA as P52100024906 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100024906
Registered on12 Mar 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BALKRISHNA RESIDENCY 2 record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Balkrishna Associates is the promoter of record on 44 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

44projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 12 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

Every home in BALKRISHNA RESIDENCY 2 is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 12 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 12 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
BALKRISHNA RESIDENCY 21G+531 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023a) Our Project- ‘BALKRISHNA RESIDENCY 2’ bearing Reg. No. P52100024906 had its initial registration valid till 31st December, 2021 which was extended for 6 months ending 30th June,
30 Jun 202330 Dec 2023We have been short of our completion schedule only due to the procedural and administrative issues with obtaining the Fire and Lift NOC authorities and pending completion of retain

Location, Land & Connectivity

Located at KONDHWA BK, TILEKARNAGAR KATRAJ-KONDHWA RD, Haveli, Pune, 411048. Per the filed land record, the plot is bounded to the north by 9MROAD, to the south by BALAJI ISCKON TEMPLE, to the east by 9M ROAD and to the west by BALKRISHNA RESIDENCY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT9 km
Pune Junction / city centre9 km
Kharadi / EON IT Park13 km
Pune Int'l Airport (Lohegaon)16 km
Baner–Balewadi belt17 km
Hinjewadi Rajiv Gandhi IT Park22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Khurd

Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kapital
possession by Dec 2026 · Ostwal Realty
Akshardham Phase 2
possession by Dec 2026 · Shreyan Ventures
Clover Highlands
possession by Dec 2026 · Clover Developers Pvt Ltd
Hagawane Landmark
Not filing quarterly progress reports · possession by Dec 2026 · Santosh Subhash Hagawane

Major developers building in Kondhwa Khurd

Other RERA-registered projects in Pune

Balkrushna Apartment
declared completion Dec 2024 · Mangaldeep Associates
Baner BIZ BAY
declared completion Dec 2019 · Baner BIZ BAY
Bangawasi
possession by Dec 2027 · NEW Front Developers
Banka Sapphire
possession by Dec 2030 · Banka Constructions
Bankar Sable Heights
possession by Mar 2027 · Yogesh Dattatray Sable
Baramati Trade Center
declared completion Dec 2025 · Vasundhara Nirmiti Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026