MahaRERA Property Intelligence · Pune

Bhagyashree

P52100078657 · Shivajinagar · promoter Uday Vasudeo Shaligram

Certificate SignedDue 31 Oct 2027

Delivery & Registration

MahaRERA registrationP52100078657
Registered on01 Jan 2025
Promoter-declared completion31 Oct 2027
Current statusCertificate Signed
Against today15 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Uday Vasudeo Shaligram is the promoter of record on 5 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~85.9% of the estimated project cost incurred as of the last certificate (₹6.15 Cr spent against a ₹7.16 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 10 homes filed with MahaRERA, 4 are sold/booked and 6 remain available (~40% sold) — selling steadily. Buyers have committed ₹6.83 Cr in agreement value so far. Of that, ₹6.13 Cr (~90%) is already collected, ₹70.57 Lakh receivable — a read on how far along these sales really are. Note: the project registers 15 homes in total, but this sold/unsold inventory filing covers only 10 of them — the other 5 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101645 sqft (59.95 sqm)₹1.45 Cr
Floor 1101A273 sqft (25.34 sqm)₹50.41 Lakh
Floor 2201645 sqft (59.95 sqm)₹1.45 Cr
Floor 2201A273 sqft (25.34 sqm)₹50.41 Lakh
Floor 2202919 sqft (85.39 sqm)₹1.95 Cr
Floor 4402919 sqft (85.39 sqm)₹1.95 Cr

⚠ The inventory filing also declares: 5 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 15 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Bhagyashree1G+515-

Unit mix on the filing: 15 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Shivajinagar, Bhamburda, Pune City, Pune, 411016. Per the filed land record, the plot is bounded to the north by Final Plot No 485C 2, to the south by Final Plot No 485C 2A, to the east by Municipal Road and to the west by Final Plot No 485C 3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shivajinagar

Jeevan Pradeep CO Operative Housing Society LTD
possession by Jul 2026 · Belvalkar Housing LLP
Narendra Housing Society
possession by Sep 2026 · Elite Infrastructure PVT LTD
Vallabh Co-Op Housing Society
possession by Sep 2026 · Srkd Landmark LLP
16 Lakaki
possession by Dec 2026 · Shah Kulkarni Associates LLP
Amrutakunj Co Operative Housing Society Limited
possession by Dec 2026 · Deshpande Realty LLP
Eshaan
possession by Dec 2026 · Naman Realty

Major developers building in Shivajinagar

Other RERA-registered projects in Pune

Bhagyashree
possession by Dec 2028 · Bhagyashree Niwas HSG SOC LTD
Bhagyashree Apartment
declared completion Dec 2021 · OM Associates
Bhagyashree Residency
declared completion Dec 2023 · Dattatray Bhagwan Beldar
Bhagyasparsh
possession by Mar 2027 · Shitole Construction
Bhagyasthan Phase1
declared completion Jul 2024 · Tulip Inn Construwell Pvt. Ltd.
Bhagyasthan Plotting
declared completion Dec 2025 · Tulip Inn Construwell Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026