MahaRERA Property Intelligence · Pune

ROHAN MADHUBAN II WINGS D E

P52100002307 · promoter Rohan

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52100002307
Registered on31 Jul 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rohan is the promoter of record on 78 projects, of which 6 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
WING D1G+1531 Dec 2021
WING E1G+1531 Dec 2021

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000010669028/02/2022SUNITA DINANATH MANOHAR vs Mr. Sanjay Lunkadorder passed

Location, Land & Connectivity

Located at Pune City, Pune, 411016. Per the filed land record, the plot is bounded to the north by 9 MTR INTERNAL ROAD, to the south by OPEN SPACE 1, to the east by AMENITY SPACE and to the west by WING A B C. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~115 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park115 km
Baner–Balewadi belt121 km
Pune Junction / city centre131 km
Pune Int'l Airport (Lohegaon)132 km
Kharadi / EON IT Park136 km
Magarpatta / Hadapsar IT136 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rohan Promoters & Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Rohan Promoters & Developers project & its RERA track record →

Other flagged projects by Rohan Promoters & Developers

Rohan Promoters & Developers
FlaggedPune

Other RERA-registered projects in Shivajinagar

Jeevan Pradeep CO Operative Housing Society LTD
possession by Jul 2026 · Belvalkar Housing LLP
Narendra Housing Society
possession by Sep 2026 · Elite Infrastructure PVT LTD
Vallabh Co-Op Housing Society
possession by Sep 2026 · Srkd Landmark LLP
16 Lakaki
possession by Dec 2026 · Shah Kulkarni Associates LLP
Amrutakunj Co Operative Housing Society Limited
possession by Dec 2026 · Deshpande Realty LLP
Eshaan
possession by Dec 2026 · Naman Realty

Major developers building in Shivajinagar

Other RERA-registered projects in Pune

Rohan Nidita Phase 1
possession by Mar 2027 · Rohan & Atul Enterprises
Rohan Nidita Phase 2
possession by Dec 2028 · Rohan & Atul Enterprises
Rohan Prathama
declared completion Dec 2024 · Rohan Housing Pvt Ltd
Rohan Residency
declared completion Dec 2022 · Namdeo Rambhau Mhetre
Rohan Saroha Phase 1
possession by Sep 2028 · Rohan Builders & Developers Private
Rohan Viti
possession by Dec 2027 · Rohan Builders & Developers Private

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026