CANVAS

Pune · PDS REALTY PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

14units filed as unsoldInventory · 13 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
18registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100009294

Delivery and registration

When is the project declared for completion?

CANVAS is registered with MahaRERA as P52100009294 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100009294
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CANVAS record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In CANVAS, 4 of 18 homes filed with MahaRERA are recorded as sold or booked, about 22%, and 14 remain available.

22%sold

4 of 18 homes

₹6.00 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹4.79 Cr (about 80%) is recorded as collected and ₹1.21 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 3A11,582 sqft (147 sqm)₹1.75 Cr
Floor 3B11,659 sqft (154.1 sqm)₹1.75 Cr
Floor 3B3-11,823 sqft (169.4 sqm)₹1.75 Cr
Floor 3B3-21,626 sqft (151.1 sqm)₹1.75 Cr
Floor 3B41,658 sqft (154 sqm)₹1.75 Cr
Floor 3B6893 sqft (83 sqm)₹1.75 Cr
Floor 3S3-011,141 sqft (106 sqm)₹80.00 Lakh
Floor 3S3-021,141 sqft (106 sqm)₹80.00 Lakh
Floor 3S3-031,345 sqft (125 sqm)₹80.00 Lakh
Floor 3S3-041,345 sqft (125 sqm)₹80.00 Lakh
Floor 3S3-051,345 sqft (125 sqm)₹80.00 Lakh
Floor 3S3-061,345 sqft (125 sqm)₹80.00 Lakh
Floor 3S3-081,345 sqft (125 sqm)₹80.00 Lakh
Floor 3S3-091,625 sqft (151 sqm)₹80.00 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CANVAS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 13 September 2026

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 4 homes carry one, and 14 of the 18 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B3-11,823 sqftRs 1.8500 cr2 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3 and 18 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A1G+3229 Dec 2019
B11G+31-
B21G+31-
B31G+32-
B41G+31-
B51G+31-
B61G+31-
S31G+39-
S11G+3--
S21G+3--

Unit mix on the filing: 18 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2025We are constructing 8 buildings consisting of 17 tenements, i.e., 9 rowhouses and 8 bungalows. Rowhouses being single building cannot be constructed in phasewise which is already c

Location, Land & Connectivity

Located at Pune, R.S. 129 Lonavala (M Cl), Mawal, Ward GNorth, Mumbai City, 410401. Per the filed land record, the plot is bounded to the north by R S 130A, to the south by R S 127, to the east by R S 127 and to the west by R S 128 AND LAYOUT ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~41 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park41 km
Baner–Balewadi belt46 km
Pune Junction / city centre57 km
Pune Int'l Airport (Lohegaon)59 km
Kharadi / EON IT Park62 km
Magarpatta / Hadapsar IT62 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lonavala

Vogue 25
possession by Oct 2026 · Goodbrick Realty Private Limited
Amoda Reserve - South Park
possession by Dec 2026 · Kalpataru Properties Private Limited
Atarkya Apartment
possession by Dec 2026 · Ankush Narayan Chaudhari
Bliss Estates
possession by Dec 2026 · Benjamin Michael Manuel
Hill Spring Enclave 4
Deregistered by MahaRERA · possession by Dec 2026 · S & S Associates
Lonavalas Finest Phase2
possession by Dec 2026 · Rahul Hanumant Satav

Other RERA-registered projects in Pune

Canvas Coconut County
declared completion Dec 2025 · Canvas Estates
Capetown Heights
possession by Jul 2030 · Anand Jadhav
Capital ONE
declared completion Oct 2024 · Swojas Icon Constructions LLP
Capital Square
declared completion Dec 2019 · GDS Buildcon Private Limited
Capri
possession by Jul 2030 · Knest Constructions LLP
Carnation
declared completion Dec 2023 · S P Homes Promoters & Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026