Pune/Project record

MahaRERA · the public record

CHAITANYA VISHWA

PAWAR WASTI · SHASHANK ANIL DADAR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2029declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100029376

Delivery and registration

When is the project declared for completion?

CHAITANYA VISHWA is registered with MahaRERA as P52100029376 and the promoter has declared completion for 31 Mar 2029.

31 Mar 2029

declared completion

30months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100029376
Registered on29 May 2021
Promoter-declared completion31 Mar 2029
Current statusCertificate Signed
Against today30 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHAITANYA VISHWA record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shashank Anil Dadar is the promoter of record on 6 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CHAITANYA VISHWA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
BUILDING A WING A1G+131 Mar 2029
BUILDING B WING A1G+531 Mar 2029
BUILDING B WING B1G+531 Mar 2029
BUILDING B WING C1G+531 Mar 2029
BUILDING C WING A1G+531 Mar 2029
BUILDING D WING A1G+331 Mar 2029

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at PAWAR WASTI, DAUND PATAS ROAD, Daund, Pune, 413801. Per the filed land record, the plot is bounded to the north by OLD SNO 100, to the south by DAUND PATAS OVER BRIDGE, to the east by SNO203 PAWAR PLOT and to the west by SNO203 KHARAT PLOT. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Daund

Shri Ashtavinayak Park
possession by Oct 2026 · Ajay Builders AND Associates Daund
Sai Capital
Not filing quarterly progress reports · possession by May 2027 · Satish Deepak Thorat
R City
possession by Mar 2028 · Reva Construction AND Developers
Shri Govind Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Developers Daund
Shri Hari Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Construction AND Developers Daund
Ekdanta
possession by Dec 2028 · M/S Prakash Construction Co.

Other RERA-registered projects in Pune

Chaitanyaram
possession by Dec 2028 · Chaitanyaram Sahakari Gruhrachana Sansth
Chaitraban Residency
declared completion Jun 2024 · Relive Construction
Chaitranagari
possession by Jun 2028 · Ruhi Omkar Developers
Chaitrangan Phase II
possession by May 2027 · Dedge Housing Development LLP
Chakan Annex
declared completion Jun 2023 · Sangam Realty
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026