MahaRERA Property Intelligence · Pune

CHAITRABAN RESIDENCY

P52100016643 · BHAIRAVNATH NAGAR · promoter Relive Construction

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP52100016643
Registered on05 Jun 2018
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Relive Construction is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
CHAITRABAN A1G+131 May 2021
CHAITRABAN B1G+631 May 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 May 202231 Dec 2023Reason for delay is due to Change in Contractor as earlier construction pace was pretty slow hence changed the contractor in month of dec, 22 & now we are aiming to close the proje
30 May 202230 Jun 2024Sir Building is almost completed we are awaiting Lift NOC and Fire NOC before getting final completion Certificate for Wing B from competent authority, as these NOC are depend on t
30 May 202230 May 2023Due to covid 19 pandemic since 2020 we face lot of difficulties in getting required material and labour on time. Now all is working well booking also flowing contentiously and we a

Location, Land & Connectivity

Located at BHAIRAVNATH NAGAR, PUNE - POUD ROAD, Mulshi, Pune, 412115. Per the filed land record, the plot is bounded to the north by 12 M ROAD, to the south by GN 319, to the east by GN 320 P and to the west by GN 314. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhugaon

Balaji Krupa
possession by Jul 2026 · Santosh Dinkar Narvekar
Manas Valley Phase II
possession by Oct 2026 · Balaji Kimaya Associates
Plot NO. B-01 TO B-21 Viva,pirangut,pune
possession by Nov 2026 · Pact Real Estate Private Limited
Frangipani, Viva, Pirangut
Deregistered by MahaRERA · possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Krushnarang Residency
possession by Dec 2026 · Vastushilp Developers
Shanaya Elegance
possession by Dec 2026 · CK Associates

Major developers building in Bhugaon

Other RERA-registered projects in Pune

Chaitranagari
possession by Jun 2028 · Ruhi Omkar Developers
Chaitrangan
declared completion Jun 2025 · Dedge Housing Development LLP
Chaitrangan Phase II
possession by May 2027 · Dedge Housing Development LLP
Chakan Annex
declared completion Jun 2023 · Sangam Realty
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP
Chakan Nagarparishad Pmay AHP
possession by Dec 2026 · Chakan Nagarparishad

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026