CHINTAMANI AASHISH

P52100011247 · promoter Rohit Labhade And

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP52100011247
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
CHINTAMANI AASHISH1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 411041. Per the filed land record, the plot is bounded to the north by ROAD, to the south by PROPERTY OF MR GULAB SHANKAR POKALE, to the east by PROPERTY OF MR BOKIL MR SURYAVANSHI AND MR MANE and to the west by PROPERTY OF MR SHIVAJI SHANKAR POKALE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~156 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park156 km
Baner–Balewadi belt161 km
Pune Int'l Airport (Lohegaon)169 km
Pune Junction / city centre171 km
Kharadi / EON IT Park173 km
Magarpatta / Hadapsar IT175 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Homedale Phase 2
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop

Major developers building in Dhayari

Other RERA-registered projects in Pune

Chintamani Capital & Vinay Residency
possession by Dec 2027 · M/S Varad Vinayak Developers
Chintamani Complex
declared completion Dec 2018 · Chintamani Associates
Chintamani Corner
declared completion Jan 2023 · Sudam Sitaram Kunjir
Chintamani Heights
declared completion Feb 2026 · Narendra Balasaheb Badave
Chintamani Heights
possession by Dec 2026 · Avadhoot Developers
Chintamani Paradise
declared completion Sep 2020 · 01/04/2017

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026