MahaRERA Property Intelligence · Pune

CLASSIC PRIDE

P52100012596 · promoter Prashant Vitthal Abhang

Certificate SignedDue 15 Aug 2019

Delivery & Registration

MahaRERA registrationP52100012596
Registered on04 Sep 2017
Promoter-declared completion15 Aug 2019
Current statusCertificate Signed
Against todayabout 83 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Prashant Vitthal Abhang is the promoter of record on 80 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
CLASSIC PRIDE1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Ambegaon, Pune, 410505. Per the filed land record, the plot is bounded to the north by 276, to the south by ROAD, to the east by 275-3 and to the west by CHANDRAKANT RAKSHE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)31 km
Hinjewadi Rajiv Gandhi IT Park33 km
Kharadi / EON IT Park34 km
Baner–Balewadi belt35 km
Pune Junction / city centre36 km
Magarpatta / Hadapsar IT38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rajgurunagar

7 Sagar Plaza
possession by Aug 2026 · Sagar Kaluram Patole
Shree Paradise
possession by Oct 2026 · Sunita Ashutosh Gosavi
Rajashri Apartments
possession by Oct 2026 · Omkar Sanjay Thigale
Classic Amrut
possession by Oct 2026 · Classic Infra
Mahalaxmi Heights
possession by Dec 2026 · Mahalaxmi Developers
Aryaa Dream Town
possession by Dec 2026 · Vini Builders AND Developers

Other RERA-registered projects in Pune

Classic Residency
declared completion Nov 2020 · Classic Developers
Cleveland Park
declared completion Oct 2025 · Vardaan Lifestyle Limited
Cliff Residences
possession by Jan 2028 · Paranjape Schemes LTD
Clone Tiara
possession by Nov 2026 · Clone Properties LLP
Clone Tiara PH-2
possession by Oct 2028 · Clone Properties LLP
Cloud 11
declared completion Dec 2018 · Sainath Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026