Pune/Project record

MahaRERA · the public record

CLOVER PARADISE

DAUND · KRUNAL RAMESH RATHOD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100053260

Delivery and registration

When is the project declared for completion?

CLOVER PARADISE is registered with MahaRERA as P52100053260 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100053260
Registered on23 Oct 2023
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CLOVER PARADISE record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CLOVER PARADISE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
CLOVER PARADISE1G+630 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DAUND, LINGALI, Daund, Pune, 413801. Per the filed land record, the plot is bounded to the north by MR MANE PLOT, to the south by 9 MTR ROAD, to the east by AMENITY SPACE and to the west by 12 MTR ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Daund

Shri Ashtavinayak Park
possession by Oct 2026 · Ajay Builders AND Associates Daund
Sai Capital
Not filing quarterly progress reports · possession by May 2027 · Satish Deepak Thorat
R City
possession by Mar 2028 · Reva Construction AND Developers
Shri Govind Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Developers Daund
Shri Hari Park
Not filing quarterly progress reports · possession by Dec 2028 · Ajay Construction AND Developers Daund
Ekdanta
possession by Dec 2028 · M/S Prakash Construction Co.

Other RERA-registered projects in Pune

Club View 1,2,3,9,10,11 LCL 0003
declared completion Dec 2021 · Lavasa Corporation Ltd
Club View 12, 13 - Lcl0005
declared completion Dec 2021 · Lavasa Corporation Ltd
Club View 4,5,6
declared completion Dec 2021 · Lavasa Corporation Ltd
Coconut County
declared completion Mar 2025 · Heritage Properties
Coconut Grove
declared completion Sep 2020 · Shree Ganesh Buildcon
Cocoon Homes
possession by Oct 2029 · Canvas Estates

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026