MahaRERA Property Intelligence · Pune

COCONUT GROVE

P52100003136 · promoter Shree Ganesh Buildcon

Certificate SignedDue 30 Sep 2020

Delivery & Registration

MahaRERA registrationP52100003136
Registered on04 Aug 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
COCONUT GROVE1G+730 Sep 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 412205. Per the filed land record, the plot is bounded to the north by LAND PROPERTY AT GAT NO 965 AND 966, to the south by MILKAT NO 154 B AND 154C, to the east by PROPERTY OF GRAMPANCHYAT and to the west by ROAD TOWARDS SHIVAPUR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre1 km
Magarpatta / Hadapsar IT6 km
Kharadi / EON IT Park8 km
Pune Int'l Airport (Lohegaon)8 km
Baner–Balewadi belt10 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kapurhol

Royal Purandar
possession by Dec 2026 · Carcanet Infra Projects Private Limited
Shree Venkatesh SAI Residency
Not filing quarterly progress reports · possession by Mar 2027 · Shree Venkatesh SAI Associates
Balaji Dham Phase-1
possession by Mar 2027 · Garva Land Deal Private Limited
Industree
possession by Feb 2028 · Dhankawade Square Realtors LLP
Navkar Pleasure
possession by Dec 2028 · Parag Properties
Pooja Heavan Park
possession by Dec 2028 · Pooja Developers

Other RERA-registered projects in Pune

Cocoon Homes
possession by Oct 2029 · Canvas Estates
Collina
declared completion Mar 2022 · Bharucha & Sons Realtors & Devel
Collina Casa
declared completion Mar 2020 · Trinetra Enterprise
Collina Vista
declared completion Apr 2022 · Rajendra Kamble
Comfort Zone
declared completion Dec 2022 · Aditya Shagun Developers
Comfort Zone Bliss
possession by Jun 2027 · Aditya Shagun Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026