Pune/Project record

MahaRERA · the public record

Crystal Space

BOPKHEL · SAI SAMARTH DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

4units filed as unsoldInventory · 18 September 2026
31 Mar 2027declared completionMahaRERA registration · read 12 Jul 2026
28registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100046408

Delivery and registration

When is the project declared for completion?

Crystal Space is registered with MahaRERA as P52100046408 and the promoter has declared completion for 31 Mar 2027.

31 Mar 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100046408
Registered on22 Jun 2022
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Crystal Space record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In Crystal Space, ₹3.54 Cr of a declared ₹4.63 Cr estimated project cost is reported as incurred, about 76.4%, as at the last certified filing with MahaRERA.

76.4%

₹3.54 Cr

of ₹4.63 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Crystal Space, 11 of 15 homes filed with MahaRERA are recorded as sold or booked, about 73%, and 4 remain available.

73%sold

11 of 15 homes

₹3.94 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹3.64 Cr (about 92%) is recorded as collected and ₹30.70 Lakh as receivable. The project registers 28 homes in total, while this sold/unsold inventory filing covers 15 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 11 registered agreements, the effective carpet rate is ₹7,022/sqft, with eight in ten falling between ₹5,269 and ₹18,746 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1Shop 101351 sqft (32.62 sqm)₹19.07 Lakh
Floor 1Shop 103171 sqft (15.85 sqm)₹9.26 Lakh
Floor 5503645 sqft (59.95 sqm)₹28.07 Lakh
Floor 5504666 sqft (61.86 sqm)₹28.97 Lakh

The inventory filing also declares: 13 owner/investor-held.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 11 homes carry one, and 4 of the 28 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
Shop 103171 sqftRs 18,746 a sq ft typical, over Rs 18,635 to Rs 20,3323 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Crystal Space, 1 of the 4 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 3 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 28 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Crystal Space1G+72831 Mar 2025

Unit mix on the filing: 18 residential and 10 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 May 202620 percent work is pending and will be completed til 31-05-2026.
31 May 202631 Mar 2027Pending Occupancy Certificate and pending site inspection/visit by the PMC Department.

Location, Land & Connectivity

Located at BOPKHEL, COLONY NO 9, GANESH NAGAR, Haveli, Pune, 411031. Per the filed land record, the plot is bounded to the north by By Vitthalanjan Heights, to the south by By Mr Ambre Property, to the east by By PMC Boundary and to the west by By Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Samarth Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Bopkhel

Ghule Pride
possession by Sep 2026 · Shravya Developers
IRA Icon
possession by Sep 2026 · Tirupati Associates
Swami Shrushti
possession by Dec 2026 · Pruthviraj Developers Through Sagar Hanu
Kundan Praangan
possession by Mar 2027 · Kundan AND Jain Developers LLP
Aksha Casa Palladium
possession by May 2027 · Accurate Realities
Abhang Recidency
possession by Jun 2027 · SAI Developers

Other RERA-registered projects in Pune

Crystal Spring
possession by Dec 2029 · Kishankumar Jugalkishor Kedia
Crystal Tower
possession by Dec 2026 · Jadhav Civil Project
Crystal Tower
possession by May 2027 · Santosh Kakasaheb Pathade
Crystal Tower Phase 2
possession by Mar 2029 · Jadhav Civil Project
Cullinan
possession by Dec 2029 · M/s Garve Corporation
Cyprus OAK
possession by Dec 2026 · S R S Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026