MahaRERA Property Intelligence · Pune

DATTHIRA COMPLEX

P52100005994 · promoter Vijaykumar Appaso Chaundkar

Certificate SignedDue 31 Jan 2021

Delivery & Registration

MahaRERA registrationP52100005994
Registered on14 Aug 2017
Promoter-declared completion31 Jan 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vijaykumar Appaso Chaundkar is the promoter of record on 29 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
DATTHIRA1G+531 Jan 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Baramati, Pune, 413115. Per the filed land record, the plot is bounded to the north by Bol, to the south by Internal Road, to the east by Road and to the west by vinod saste. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~184 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Junction / city centre183 km
Magarpatta / Hadapsar IT184 km
Baner–Balewadi belt184 km
Hinjewadi Rajiv Gandhi IT Park186 km
Kharadi / EON IT Park188 km
Pune Int'l Airport (Lohegaon)191 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vijaykumar Appaso Chaundkar is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Vijaykumar Appaso Chaundkar

Vijaykumar Appaso Chaundkar
FlaggedPune

Other RERA-registered projects in Malegaon

Shripal Park
Not filing quarterly progress reports · possession by Mar 2027 · Shripal Landmarks AOP
Brahma Chaitanya Complex
possession by Mar 2028 · Ninad Bhimrao Mane
Ramraj Residency
possession by Dec 2028 · Ramchandra Dinkar Devkate
Shri Bhavani Market
Not filing quarterly progress reports · possession by Apr 2029 · Shri Bhavani Shankar Developers
Ramraj Residency B Building
possession by Dec 2030 · Ramchandra Dinkar Devkate
Anandwan Apartment
Not filing quarterly progress reports · declared completion Dec 2025 · Rudransh Infra

Other RERA-registered projects in Pune

Daulat Heights
declared completion Jun 2018 · M/S B.k. Developers
Daulat Park-1
possession by Dec 2027 · BMK Properties Private Limited
Daulat Park-2
possession by Dec 2027 · BMK Properties Private Limited
Davbindu Apartment
declared completion Jun 2023 · Hemant Ankush Balwadkar
Dayalheights
declared completion Jun 2019 · Vinod Premchand Chandwani
DB Commercial Phase I
declared completion Nov 2021 · Pune Buildtech Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026