DHANMAI COMPLEX

KATRAJ · RAVINDRA DHANRAJ RATHI

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014621

Delivery and registration

When is the project declared for completion?

DHANMAI COMPLEX is registered with MahaRERA as P52100014621 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014621
Registered on15 Dec 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DHANMAI COMPLEX record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ravindra Dhanraj Rathi is the promoter of record on 99 projects registered with MahaRERA, 21 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

99projects

registered with MahaRERA

21flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DHANMAI COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
DHANMAI COMPLEX1G+631 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KATRAJ, NEAR KATRAJ, Haveli, Pune, 411046. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by SR NO 18 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre8 km
Magarpatta / Hadapsar IT9 km
Kharadi / EON IT Park13 km
Pune Int'l Airport (Lohegaon)15 km
Baner–Balewadi belt15 km
Hinjewadi Rajiv Gandhi IT Park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambegaon Bk

Amits Bloomfield Phase III - J AND K Building
possession by Sep 2026 · Amit Enterprises Housing Limited
Ankur Residency
possession by Oct 2026 · Ankur Developers
Astonia Royale Phase III - P Building
possession by Oct 2026 · Amit Enterprises Housing Limited
Airavat B Wing
possession by Nov 2026 · Ashtavinayak Developers
Rajyog C Wing
possession by Dec 2026 · Santosh Shankar Tathe
Deveshwar Tekadi- Phase I- Building: A,b,c,d,e
Not filing quarterly progress reports · possession by Dec 2026 · Mahadrishti Spaces LLP

Major developers building in Ambegaon Bk

Other RERA-registered projects in Pune

Dhanwantari Terrace Cooperative Housing Society Limited
declared completion Dec 2017 · Digamber Parulekar
Dhara Icon
declared completion Dec 2023 · D R Bhondve Properties
Dharampal Corporate Avenue
possession by Dec 2026 · Surender Dharampal Agarwal
Dhareshwar Angan
declared completion Jan 2026 · Shree Vighnaharta Construction Group
Dharmesh
declared completion Dec 2025 · Pandit Javdekar Associates
Dharti Green
possession by Jan 2027 · Dharti Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026