Pune/Project record

MahaRERA · the public record

ECO VALLEY

Pune · MKR BUILDCON PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014127

Delivery and registration

When is the project declared for completion?

ECO VALLEY is registered with MahaRERA as P52100014127 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014127
Registered on09 Nov 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ECO VALLEY record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ECO VALLEY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
BUILDING A1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Oct 2019Due to Strike off company as per Companies act.2013 . We unable to complete project within due date so we here request to approve proposed extended date, Also attached strike off r
31 Oct 201931 Dec 2021DUE TO MARKET DOWN . STRICK OUT OF COMPANY

Location, Land & Connectivity

Located at Khed, Pune, 410505. Per the filed land record, the plot is bounded to the north by 124-2 -NEW TO THE NORTH, to the south by 123 121 -NEW TO THE NORTH TO THE SOUNT, to the east by 120-NEW TO THE EAST and to the west by 15M VILLAGE ROAD TO NORTH TO THE WEST. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~24 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park24 km
Baner–Balewadi belt29 km
Pune Junction / city centre39 km
Pune Int'l Airport (Lohegaon)39 km
Kharadi / EON IT Park43 km
Magarpatta / Hadapsar IT44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rajgurunagar

Kohinoor Heights
possession by Oct 2026 · Abbas Ayub Ansari
Shree Paradise
possession by Oct 2026 · Sunita Ashutosh Gosavi
Rajashri Apartments
possession by Oct 2026 · Omkar Sanjay Thigale
Classic Amrut
possession by Oct 2026 · Classic Infra
Mahalaxmi Heights
possession by Dec 2026 · Mahalaxmi Developers
Aryaa Dream Town
possession by Dec 2026 · Vini Builders AND Developers

Major developers building in Rajgurunagar

Other RERA-registered projects in Pune

ECO Valley Plus
declared completion Apr 2022 · Namrata Jalan Ventures
ECO Villas
declared completion Aug 2018 · Saptarshi Properties
ECO Villas II
declared completion Apr 2019 · Saptarshi Properties
Ecogram
declared completion Dec 2020 · Shri Siddhivinayak Builders
Ecogram
declared completion Dec 2020 · Shri Siddhivinayak Builders
Ecopolitan Phase I
possession by Dec 2026 · Iftekhar Peerpashahusseni Inamdar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026