Pune/Project record

MahaRERA · the public record

EKNATH AHER VAIBHAV

PIRANGUT · CHANDRAKANT EKNATH AHER

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014744

Delivery and registration

When is the project declared for completion?

EKNATH AHER VAIBHAV is registered with MahaRERA as P52100014744 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

87months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014744
Registered on26 Dec 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EKNATH AHER VAIBHAV record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Chandrakant Eknath Aher is the promoter of record on 121 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

121projects

registered with MahaRERA

23flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for EKNATH AHER VAIBHAV in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A B1G+730 Jun 2018
C D1G+730 Jun 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2019ALMOST 80% WORK HAS BEEN ALREADY COMPLETED AS ON DATE. WORK WAS STOOPED AT THE TIME OF RERA, DUE TO NON BOOKING OF FLAT. NOW IT IS RESUMED, HENCE I AM VERY MUCH SURE ABOUT COMPLETI

Location, Land & Connectivity

Located at PIRANGUT, PAUD ROAD, Mulshi, Pune, 412014. Per the filed land record, the plot is bounded to the north by GAT NO 1621, to the south by GAT NO 1619 OLD, to the east by ROAD and to the west by CHANDRAKANT EKNATH AHER PLOT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt6 km
Hinjewadi Rajiv Gandhi IT Park10 km
Pune Junction / city centre12 km
Magarpatta / Hadapsar IT17 km
Pune Int'l Airport (Lohegaon)19 km
Kharadi / EON IT Park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pune

EL Regalo
possession by Dec 2026 · Mahesh Realtors
ELA Homes
declared completion Dec 2024 · Liquid Properties
Elanza
declared completion Dec 2025 · Santosh Mariba Bagadi
Elara
possession by Jun 2029 · Regenesis Project Management LLP
Elate
possession by Oct 2027 · M/s. Guddwill RVN Spaces LLP
Elegance
declared completion Jun 2023 · Ulhas Dnyaneswar Konde

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026