MahaRERA Property Intelligence · Pune

Emerald Park B Building

P52100020362 · Pimpri Chinchwad · promoter Balasaheb Vyankatrao Gaikwad

Certificate SignedDue 30 Jul 2022

Delivery & Registration

MahaRERA registrationP52100020362
Registered on05 Apr 2019
Promoter-declared completion30 Jul 2022
Current statusCertificate Signed
Against todayabout 48 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Balasaheb Vyankatrao Gaikwad is the promoter of record on 5 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
Emerald Park B Building1G+1630 Jul 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Pimpri Chinchwad, Main road, Haveli, Pune, 411044. Per the filed land record, the plot is bounded to the north by S No 50 P, to the south by 18 M WIDE DP ROAD, to the east by S No 50 5 and to the west by 18 M WIDE DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Balasaheb Vyankatrao Gaikwad is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Balasaheb Vyankatrao Gaikwad

Balasaheb Vyankatrao Gaikwad
FlaggedPune

Other RERA-registered projects in Nigdi

Swastik Platinum
possession by Jul 2026 · Swastik Infinity
THE Saga
possession by Sep 2026 · Nest Saswad Realty LLP
Aashirwad Homes
possession by Dec 2026 · Nest Saswad Realty LLP
Paradise Residency
possession by Dec 2026 · Balaji Developers
Shuban Enclave
possession by Dec 2026 · Sahyadri Devcon
Vision Vanessa
possession by Dec 2026 · P4 Group

Other RERA-registered projects in Pune

Emerald PH-IV
declared completion Jun 2019 · Gawade Construction Company
Emerald Skies
possession by Jan 2028 · Rajyog Group
Emerald Tower
declared completion Jun 2025 · Solitere Space & Development
Emerald Towers
declared completion Jun 2026 · Samruddhi Developers
Emerald Villas
possession by Dec 2029 · Ashwin Arvind Sanghvi
Emerald Vista
declared completion Jun 2026 · Padmavati Landmarks

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026