FOREST TRAIILS

P52100009038 · promoter Champion Builders Developers

Certificate SignedDue 11 Nov 2022

Delivery & Registration

MahaRERA registrationP52100009038
Registered on19 Aug 2017
Promoter-declared completion11 Nov 2022
Current statusCertificate Signed
Against todayabout 44 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
FOREST TRAIILS1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 410401. Per the filed land record, the plot is bounded to the north by FOREST, to the south by PLOT NO 2, to the east by S NO 68 and to the west by S NO 64 DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~40 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park40 km
Baner–Balewadi belt45 km
Pune Junction / city centre56 km
Pune Int'l Airport (Lohegaon)58 km
Kharadi / EON IT Park61 km
Magarpatta / Hadapsar IT61 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lonavala

Vogue 25
possession by Oct 2026 · Goodbrick Realty Private Limited
Doodle Homes
possession by Dec 2026 · Doodle Homes LLP
Amoda Reserve - South Park
possession by Dec 2026 · Kalpataru Properties Private Limited
Atarkya Apartment
possession by Dec 2026 · Ankush Narayan Chaudhari
Bliss Estates
possession by Dec 2026 · Benjamin Michael Manuel
Hill Spring Enclave 4
Deregistered by MahaRERA · possession by Dec 2026 · S & S Associates

Other RERA-registered projects in Pune

Forest Trails Athashri - B2
declared completion Jul 2024 · Paranjape Schemes Limited
Forest Trails Athashri B3
possession by Sep 2029 · Lavim Developers PVT LTD
Forest Trails Everglades H3 And H4
declared completion Dec 2025 · Paranjape Schemes LTD
Forest Trails Highland Tower 7 And 8
declared completion Mar 2018 · Paranjape Schemes Limited
Forest Trails Highland Tower 9, 10 And 11
declared completion Dec 2024 · Paranjape Schemes Limited
Forest View
declared completion Dec 2024 · Seven Seas Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026