MahaRERA Property Intelligence · Pune

GANGA TRUENO TOWER B

P52100002884 · promoter Kappa Realtors Llp

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52100002884
Registered on04 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kappa Realtors Llp is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
TOWER B1G+12-

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000006458007/09/2020SANDEEP vs KAPPA REALTORSorder passed
CC00500000008529805/04/2021Sandeep Singh vs Kappa Realtors LLPorder passed
CC00500000009582109/12/2021Rahul Lala vs Goel Ganga Developersorder passed
CC1250132021/04/2025Amarnath Nakul chandra Roy vs KAPPA REALTORS LLPpending / no order on file
CC1260106226/02/2026KAPPA REALTORS LLP vs AMARNATH ROYpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Dec 2022WRIT PETITION (ST.) NO.92215 OF 2020, IA 1552/2021 - by Usha Kshirsagar (Hereinafter referred as Said litigation). The captioned Petition is filed by Union of India raising various

Location, Land & Connectivity

Located at Pune City, Pune, 411047. Per the filed land record, the plot is bounded to the north by 20M DP ROAD, to the south by ADJ TO S NO 233A, to the east by V I P ROAD and to the west by 20M DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Int'l Airport (Lohegaon)115 km
Pune Junction / city centre117 km
Kharadi / EON IT Park119 km
Magarpatta / Hadapsar IT121 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lohegaon

Nivasa Enchante Phase 2
possession by Aug 2026 · Nivasa Associates
Aayush Exotica
possession by Sep 2026 · Aayush Properties
Chandan Heritage
possession by Sep 2026 · City Developers
Youthika
possession by Oct 2026 · Krushnarang Group
Easterlia
possession by Dec 2026 · Spacemint Realty LLP
Pankaj Aasmaan Phase V
possession by Dec 2026 · Pankaj Developers

Major developers building in Lohegaon

Other RERA-registered projects in Pune

Ganga Utopia Commercial
possession by Dec 2026 · Goel Ganga Developments LLP
Ganga Utopia E Building
possession by Dec 2026 · Goel Ganga Developments LLP
Ganga Vasant
possession by Jun 2028 · Ganraj Township LLP
Gangadhar
possession by Mar 2027 · Lagoo Apte Developers
Gangadhar Apartments
possession by Aug 2026 · Kelkar Housing LLP
Gangadwar CO-Operative Housing Society Limited
declared completion Dec 2025 · Vinod Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026