Pune/Project record

MahaRERA · the public record

Garden Enclave

- · REMONESA ENTERPRISES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

43units filed as unsoldInventory · 12 September 2026
30 Jun 2028declared completionMahaRERA registration · read 12 Jul 2026
44registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100006194

Delivery and registration

When is the project declared for completion?

Garden Enclave is registered with MahaRERA as P52100006194 and the promoter has declared completion for 30 Jun 2028.

30 Jun 2028

declared completion

21months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100006194
Registered on14 Aug 2017
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today21 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Garden Enclave record 43 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Remonesa Enterprises Llp is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Garden Enclave, 1 of 44 homes filed with MahaRERA are recorded as sold or booked, about 2%, and 43 remain available.

2%sold

1 of 44 homes

₹32.69 Lakh

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Garden Enclave in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 September 2026

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 1 homes carry one, and 43 of the 44 are recorded unsold.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11 and 44 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
H1G+1144-

Unit mix on the filing: 44 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Cjsd8572018Awaiting Summons
District Judge And Addl Sessions Judge Pune232018Closed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 20281. The project stands at 75% completion. 2. The consent of 100% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaini

Location, Land & Connectivity

Located at -, -, Haveli, Pune, 411048. Per the filed land record, the plot is bounded to the north by Drive Way Garden and Club of DSK Garden Enclave, to the south by By 9-15 Mtrs Road, to the east by By DSK Garden Enclave Enterance Gate Drive Way and to the west by By Sur No 37-27 Kumar Builders. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT6 km
Pune Junction / city centre7 km
Kharadi / EON IT Park11 km
Pune Int'l Airport (Lohegaon)13 km
Baner–Balewadi belt16 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Khurd

Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kapital
possession by Dec 2026 · Ostwal Realty
Akshardham Phase 2
possession by Dec 2026 · Shreyan Ventures
Clover Highlands
possession by Dec 2026 · Clover Developers Pvt Ltd
Hagawane Landmark
Not filing quarterly progress reports · possession by Dec 2026 · Santosh Subhash Hagawane

Major developers building in Kondhwa Khurd

Other RERA-registered projects in Pune

Garima Residency Building NO. 2
declared completion Dec 2024 · Garima Enterprises
Garli Heritage
declared completion May 2023 · Vsquare Incorp
Garud House Apartment Condominium
possession by Dec 2026 · Fortune Developers
Garve Buildcon O Wing 57 Avenue
possession by Dec 2026 · Garve Buildcon O Wing 57 Avenue
GAT NO 833P Village- Shindavane
declared completion Oct 2025 · Nilesh Gulab Choudhary
Gateway
declared completion Jun 2026 · Raichandani Constructions Private Limite

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026