Garden Enclave

P52100006194 · - · promoter Remonesa Enterprises Llp

Certificate SignedDue 30 Jun 2028

Delivery & Registration

MahaRERA registrationP52100006194
Registered on14 Aug 2017
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today23 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Remonesa Enterprises Llp is the promoter of record on 3 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 44 homes filed with MahaRERA, 1 are sold/booked and 43 remain available (~2% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹32.69 Lakh in agreement value so far. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11 and 44 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
H1G+1144-

Unit mix on the filing: 44 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Cjsd8572018Awaiting Summons
District Judge And Addl Sessions Judge Pune232018Closed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201930 Jun 20281. The project stands at 75% completion. 2. The consent of 100% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaini

Location, Land & Connectivity

Located at -, -, Haveli, Pune, 411048. Per the filed land record, the plot is bounded to the north by Drive Way Garden and Club of DSK Garden Enclave, to the south by By 9-15 Mtrs Road, to the east by By DSK Garden Enclave Enterance Gate Drive Way and to the west by By Sur No 37-27 Kumar Builders. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT6 km
Pune Junction / city centre7 km
Kharadi / EON IT Park11 km
Pune Int'l Airport (Lohegaon)13 km
Baner–Balewadi belt16 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Bk

Alcon Signare
possession by Jul 2026 · Alcon Builders
Vrundavan Residency
possession by Sep 2026 · Gangai Developers
Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kunj
possession by Nov 2026 · Bace India Developers
THE Latitude - D
possession by Dec 2026 · Ahura Builders

Major developers building in Kondhwa Bk

Other RERA-registered projects in Pune

Garden View
declared completion Dec 2023 · Moraya Associates
Gardenia Crest
declared completion Apr 2025 · Rujuta Shelters
Garima Residency Building NO. 2
declared completion Dec 2024 · Garima Enterprises
Garli Heritage
declared completion May 2023 · Vsquare Incorp
Garud House Apartment Condominium
possession by Dec 2026 · Fortune Developers
Garve Buildcon O Wing 57 Avenue
possession by Dec 2026 · Garve Buildcon O Wing 57 Avenue

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026