GREEN PARK PHASE 3

P52100008361 · promoter Rajendra Vasantrao Ingole

Certificate SignedDue 30 Jun 2019

Delivery & Registration

MahaRERA registrationP52100008361
Registered on18 Aug 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rajendra Vasantrao Ingole is the promoter of record on 38 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
ROW HOUSE NO F1G+1-
ROW HOUSE NO H1G+1-
ROW HOUSE NO G1G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Baramati, Pune, 413133. Per the filed land record, the plot is bounded to the north by GAT NO 51 53, to the south by ROAD 15 M, to the east by ROAD 9 M OPEN SPACE and to the west by AMMINITY SPACE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~82 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT82 km
Kharadi / EON IT Park82 km
Pune Int'l Airport (Lohegaon)86 km
Pune Junction / city centre87 km
Baner–Balewadi belt98 km
Hinjewadi Rajiv Gandhi IT Park103 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rui

Mayureshwar Mall
possession by Oct 2026 · Mayureshwar Associates
Muktai Prime
possession by Dec 2026 · New Muktai Builders
Subhadra Phase 3
possession by Dec 2026 · Subhadra Constructions
Rajnakshatra Palace
possession by Mar 2027 · Devgiri Buildcon
Mayureshwar Pride
possession by Apr 2027 · Mayureshwar Construction
Ankur Infra
possession by Mar 2028 · Ankur Infra

Other RERA-registered projects in Pune

Green Park Phase 4
declared completion Dec 2022 · Muktai Builders & Developers
Green Park Plot 1
declared completion Jun 2025 · Malpani Properties
Green Park Plot 2
declared completion Aug 2024 · Malpani Properties
Green Park Residency
declared completion Dec 2023 · Harsh Buildcon
Green Park Residency
declared completion Dec 2025 · Arun Bandu Nanaware
Green Republic
declared completion Jun 2019 · Samrat Buildcon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026