HM ROYAL

P52100028047 · KONDHWA BUDRUK, PUNE · promoter Arti Properties Private

Certificate SignedDue 30 Oct 2024

Delivery & Registration

MahaRERA registrationP52100028047
Registered on27 Jan 2021
Promoter-declared completion30 Oct 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Arti Properties Private is the promoter of record on 53 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
3B1G+1430 Apr 2024
3C1G+1430 Apr 2024
3D1G+1330 Apr 2024
5A1G+1330 Apr 2024
5C1G+1330 Apr 2024

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250308802/09/2025Imran Kasam Kachhi vs ARTI PROPERTIES PRIVATE LIMITEDorder passed

Location, Land & Connectivity

Located at KONDHWA BUDRUK, PUNE, S NO 18/19, OPPOSITE TALAB FACTORY, Mumbai City, Mumbai City, 411048. Per the filed land record, the plot is bounded to the north by S NO 18 PART S NO 19 PART, to the south by S NO 18 PART, to the east by S NO 19 PART and to the west by S NO 17 PART S NO 18 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Bk

Alcon Signare
possession by Jul 2026 · Alcon Builders
Vrundavan Residency
possession by Sep 2026 · Gangai Developers
Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kunj
possession by Nov 2026 · Bace India Developers
THE Latitude - D
possession by Dec 2026 · Ahura Builders

Major developers building in Kondhwa Bk

Other RERA-registered projects in Pune

Hollyhock City
declared completion Jul 2019 · Kate Moze Associates
Hollyhock City Building NO 2 Wing D
possession by Mar 2027 · Kate Mozze Associates
Hollyhock City Building No.5 Wing E1 & E2
possession by Dec 2029 · Kate Mozze Associates
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Homedale Imperia
possession by Dec 2028 · M/s. Om Shiv Sai Promoters & Develop
Homedale Phase 2
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026