Pune/Project record

MahaRERA · the public record

INDRAPRASTHA LANDMARK

KONDHWA BK · INDRAPRASTHA INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100022668

Delivery and registration

When is the project declared for completion?

INDRAPRASTHA LANDMARK is registered with MahaRERA as P52100022668 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100022668
Registered on10 Oct 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for INDRAPRASTHA LANDMARK record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Indraprastha Infra is the promoter of record on 12 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for INDRAPRASTHA LANDMARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
BUILDING A1G+531 Dec 2020
BUILDING B1G+1231 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KONDHWA BK, GANGADHAM SHATRUNJAY MANDIR ROAD, Pune City, Pune, 411048. Per the filed land record, the plot is bounded to the north by RATHOD PROPERTY, to the south by SR NO 65 PART, to the east by BADGARE AND KHATAPE PROPERTY and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Indraprastha Infra is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Kondhwa Khurd

Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kapital
possession by Dec 2026 · Ostwal Realty
Akshardham Phase 2
possession by Dec 2026 · Shreyan Ventures
Clover Highlands
possession by Dec 2026 · Clover Developers Pvt Ltd
Hagawane Landmark
Not filing quarterly progress reports · possession by Dec 2026 · Santosh Subhash Hagawane

Major developers building in Kondhwa Khurd

Other RERA-registered projects in Pune

Indraprastha Paradise
declared completion Dec 2019 · S. S. Developers
Indraprastha Utsav
declared completion Dec 2025 · Indraprastha Associates
Indraprasthanagari-Phase 1
declared completion Jun 2024 · D.b.developers LTD
Indrashri
possession by Jun 2027 · B U Bhandari Buildcon LLP
Indrayani Puram
declared completion Dec 2024 · Shivkrupa Developers
Indrayani Riverview Residency
declared completion Jun 2026 · Shreenath Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026