Pune/Project record

MahaRERA · the public record

JADHAV PLATINUM

AMBEGAON BUDRUK · SWARAJ DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100034865

Delivery and registration

When is the project declared for completion?

JADHAV PLATINUM is registered with MahaRERA as P52100034865 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100034865
Registered on28 Apr 2022
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JADHAV PLATINUM record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Swaraj Developers is the promoter of record on 37 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

37projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JADHAV PLATINUM in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
JADHAV PLATINUM1G+730 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at AMBEGAON BUDRUK, AMBEGAON BK, Haveli, Pune, 411046. Per the filed land record, the plot is bounded to the north by S N 45 HISSA 2 GUT4, to the south by S N 45 HISSA 2 GUT 2, to the east by S N 45 HISSA 1 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park9 km
Baner–Balewadi belt9 km
Pune Int'l Airport (Lohegaon)10 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Swaraj Developers is the promoter on 8 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Swaraj Developers project & its RERA track record →

Other flagged projects by Swaraj Developers

Other RERA-registered projects in Ambegaon Bk

Amits Bloomfield Phase III - J AND K Building
possession by Sep 2026 · Amit Enterprises Housing Limited
Ankur Residency
possession by Oct 2026 · Ankur Developers
Astonia Royale Phase III - P Building
possession by Oct 2026 · Amit Enterprises Housing Limited
Airavat B Wing
possession by Nov 2026 · Ashtavinayak Developers
Rajyog C Wing
possession by Dec 2026 · Santosh Shankar Tathe
Deveshwar Tekadi- Phase I- Building: A,b,c,d,e
Not filing quarterly progress reports · possession by Dec 2026 · Mahadrishti Spaces LLP

Major developers building in Ambegaon Bk

Other RERA-registered projects in Pune

Jadhav Prrestige
declared completion Dec 2025 · Chaandrai Vsbs Construction
JAG River View
possession by Dec 2027 · M/S JAG Spaces LLP
JAG Solitaire
possession by Jul 2027 · M/S JAG Solitaire
Jagannath Heritage
possession by Mar 2027 · Ascent Landmarks
Jagdamb Heights
declared completion Sep 2018 · Arihant Rahi Promoters
Jagdamba Heights
declared completion Mar 2026 · Sandip Laxman Jaypatre

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026