MahaRERA Property Intelligence · Pune

KAMALA KASTURI

P52100011567 · promoter Mehul Suresh Garg

Certificate SignedDue 16 Oct 2022

Delivery & Registration

MahaRERA registrationP52100011567
Registered on31 Aug 2017
Promoter-declared completion16 Oct 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mehul Suresh Garg is the promoter of record on 167 projects, of which 21 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
BUILDING1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Honorable Civil Judge Junior Division Pimpri Pune86/20162016For Hearing

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
16 Oct 202226 Dec 2019Construction of the project is completed in all respect, but legal procedures to get the completion certificate from the authorities are in process and we will require 1 year time
16 Oct 202216 Apr 2022We have applied for Completion of Project to local Muncipal corporation but to COVID-19 situation documents are not yet processed by local authorities hence extentionn required

Location, Land & Connectivity

Located at Pune City, Pune, 411026. Per the filed land record, the plot is bounded to the north by CTC 4384P, to the south by ROAD, to the east by CTC 4387P and to the west by ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~109 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park109 km
Baner–Balewadi belt115 km
Pune Junction / city centre125 km
Pune Int'l Airport (Lohegaon)126 km
Kharadi / EON IT Park130 km
Magarpatta / Hadapsar IT131 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhosari

Shrikisan Enclave
possession by Jul 2026 · M/s. Tirupathi Properties Through Prop M
Ellora Shopee
possession by Sep 2026 · Ellora Realities Private Limited
Atlantis
possession by Dec 2027 · Atharva Buildwell
Santiago Skyworld
possession by Jun 2028 · Santiago Realtech
TEN BKC
possession by Dec 2029 · Mahalaxmi Land Developers
Mahadeo Dreams
declared completion May 2026 · Shree Ganesh Associates

Other RERA-registered projects in Pune

Kamalapark CO-OP Hsg. Society
possession by Aug 2027 · Vishwam Realtors
Kamalaraj Athens B And C
possession by Jun 2027 · Kamalraj Estate
Kamalini
possession by Dec 2029 · Dreamforge Ventures LLP
Kamalraj Akshardham A Building
possession by Dec 2028 · Kamalraj Estate
Kamalraj Akshardham B And C Building
possession by Dec 2028 · Kamalraj Estate
Kamalraj Athens A
possession by Jun 2027 · Kamalraj Estate

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026