MahaRERA Property Intelligence · Pune

Kanchan Vrundavan Business Complex SHOPS 1-42

P52100011104 · promoter Kanchan Properties

Certificate SignedDue 31 Dec 2017

Delivery & Registration

MahaRERA registrationP52100011104
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 103 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kanchan Properties is the promoter of record on 18 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Ground Floor Shops 1 to 421G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Judicial Magistrate First Class Pune1303/20022002Pending
Judicial Magistrate First Class Pune319/20152015Pending

Location, Land & Connectivity

Located at Pune City, Pune, 412202. Per the filed land record, the plot is bounded to the north by by remaining part of gat number 196, to the south by by road, to the east by Gat no 197 and 199 and to the west by gat no 186 to 195 and 200. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~83 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park83 km
Baner–Balewadi belt88 km
Pune Int'l Airport (Lohegaon)97 km
Pune Junction / city centre98 km
Kharadi / EON IT Park101 km
Magarpatta / Hadapsar IT103 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Uruli Kanchan

Siddhi Sankul
possession by Sep 2026 · Jitendra Constructions AOP
Elite II
Not filing quarterly progress reports · possession by Dec 2026 · Landmark Development Corporation PVT LTD
Srinivas Empire
Not filing quarterly progress reports · possession by Mar 2027 · Srinivas And Associates
Sahyadri
possession by Aug 2027 · Sahyadri Builders And Developers
Needam - Block A - Wing B
possession by Dec 2027 · Raut Patil Constructions
Green Fantasy Phase-I
possession by Dec 2027 · Shree Mangalmurti Associates Phase-I

Other RERA-registered projects in Pune

Kanchanpuram
possession by Jun 2028 · Balaji Hari Developers AOP
Kanha AND Yashoda
declared completion Apr 2024 · Vainateya Build Private Limited
Kanha Vihar
declared completion Dec 2022 · Samarthrealities
Kanhaiya Business Centre
declared completion Dec 2025 · Sanjay Vasantlal Gundecha
Kanhaiya Majesty
declared completion Dec 2021 · Shriram Infracon
Kanishka Grand Plaza
possession by Dec 2026 · Platinum Lifespace Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026