KATE SQUARE

Pune · KATE BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013025

Delivery and registration

When is the project declared for completion?

KATE SQUARE is registered with MahaRERA as P52100013025 and the promoter has declared completion for 01 Dec 2021.

01 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013025
Registered on12 Sep 2017
Promoter-declared completion01 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KATE SQUARE record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KATE SQUARE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
K101G+1131 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Senior Division Pune3482016Open

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered01 Dec 2020The construction work up to 7th floor including parking is complete, as also seen from Architect’s certificate and Part completion certificate (Sr.No.82/2019) for the same is alre

Location, Land & Connectivity

Located at Haveli, Pune, 411061. Per the filed land record, the plot is bounded to the north by 9 MTR INTERNAL ROAD, to the south by AMENITY PLOT, to the east by PLOT NO 3 PLUS 4 and to the west by 18 MTR DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt6 km
Hinjewadi Rajiv Gandhi IT Park8 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)11 km
Kharadi / EON IT Park14 km
Magarpatta / Hadapsar IT14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kate Builders is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Kate Builders

Other RERA-registered projects in Pimple Gurav

Dwarkadhish Apartment
possession by Oct 2026 · Vishal Pravin Tank
Krishna Prabha Aangan
possession by Nov 2026 · Rathod AND Sons
1 Priority Rathod Business Zone
possession by Dec 2026 · Shreeji Developers
Eastern River Residency Wing D
possession by Dec 2026 · Not Available
Akshay Vista
possession by May 2027 · Akshay Skyscrapers Private Limited
7 Avenue
possession by Feb 2028 · Destiny Developers

Other RERA-registered projects in Pune

Kate Vrundavan
declared completion Apr 2021 · Vrundavan Developers
Kaustubh Realty Plot B
declared completion Jun 2025 · Santosh Bhagwandas Zanwar
Kaustubh Realty Plot C
possession by Jun 2027 · Santosh Bhagwandas Zanwar
Kavish Residency
possession by Sep 2026 · Damle Gandhe LLP
Kavita & Nav Kavita Co-Op. Hsg. Soc
possession by Apr 2029 · OM Buildcon
Kawade Patil Residency
declared completion Jan 2021 · Chaitanya Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.