Not filing quarterly progress reports · possession by Dec 2026 · Satish Bora AND Associates
Not filing quarterly progress reports · possession by Dec 2026 · Satish Bora AND Associates
MahaRERA Property Intelligence · Pune
P52100008908 · Warje · promoter Kalyan Jagannath Jadhav
| MahaRERA registration | P52100008908 |
| Registered on | 19 Aug 2017 |
| Promoter-declared completion | 30 Jun 2026 |
| Current status | Certificate Signed |
| Against today | about 1 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Kalyan Jagannath Jadhav is the promoter of record on 33 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
MahaRERA's cost filing puts construction at ~97.3% of the estimated project cost incurred as of the last certificate (₹62.45 Cr spent against a ₹64.15 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 160 homes filed with MahaRERA, 58 are sold/booked and 102 remain available (~36% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹61.44 Cr in agreement value so far. Of that, ₹52.37 Cr (~85%) is already collected, ₹9.06 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 58 registered agreements, the effective carpet rate is ₹9,882/sqft (typical range ₹7,481–₹14,998) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 160 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| A | 1 | G+12 | 40 | - |
| B | 1 | G+12 | 40 | - |
| C | 1 | G+12 | 40 | - |
| D | 1 | G+12 | 40 | - |
Unit mix on the filing: 144 residential and 16 non-residential (shops/offices).
1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000127102 | 10/06/2022 | Natwar Hariprasad Agrawal vs Kalyan Jagannath Jadhav | order passed |
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Civil Court Senior Division Pune | 201537/2006 | 2006 | Filing Of Afidavit |
The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 29 Mar 2025 | 29 Mar 2025 | a) Our Project- ‘KJ TOWER bearing Reg. No. P52100008908 has its initial registration valid till 30th March, 2024. b) Our project is in progress which is indicated by the latest F |
| 30 Mar 2024 | 30 Sep 2025 | Due to some financial and litigation problems. |
| 30 Mar 2024 | 31 Mar 2026 | Due to some financial, Government Approvals and litigation problems. |
| 30 Mar 2024 | 30 Jun 2026 | The project timeline has been adjusted by three months to facilitate the finalization of outstanding construction work and the procurement of essential statutory clearances, includ |
Located at Warje, 113, Urit Nagar, Pune City, Pune, 411058. Per the filed land record, the plot is bounded to the north by PLAYGROUND RESERVATION, to the south by 12 M SERVICE ROAD, to the east by SNo 114 and to the west by 18 M DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Baner–Balewadi belt | 8 km |
| Pune Junction / city centre | 10 km |
| Hinjewadi Rajiv Gandhi IT Park | 13 km |
| Magarpatta / Hadapsar IT | 14 km |
| Pune Int'l Airport (Lohegaon) | 17 km |
| Kharadi / EON IT Park | 17 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in KJ TOWER?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026