KOHINOOR BEGONIA PHASE III

varale phata · KOHINOOR ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100008679

Delivery and registration

When is the project declared for completion?

KOHINOOR BEGONIA PHASE III is registered with MahaRERA as P52100008679 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100008679
Registered on19 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KOHINOOR BEGONIA PHASE III record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kohinoor Associates is the promoter of record on 40 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

40projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KOHINOOR BEGONIA PHASE III in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
B-51G+1331 Dec 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for KOHINOOR BEGONIA PHASE III, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250053616/02/2025kohinoorbegonya B cooperative Housing society Ltd President Amol Mane (society) vs KOHINOOR ASSOCIATESorder passed

A co-operative housing society is recorded as the complainant (kohinoorbegonya B cooperative Housing society Ltd President Amol Mane), and MahaRERA has passed an order.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020The building is completed and process for obtaining NOCs to apply for completion certificate is underway. Due to change in Planning Authority i.e. PMRDA, the basic set of rules and

Location, Land & Connectivity

Located at varale phata, varale-Ambi road, Pune City, Pune, 410507. Per the filed land record, the plot is bounded to the north by SURVEY NO 51 HISSA NO 2 SUB DIVISION 1, to the south by SURVEY NO 51 HISSA NO 2, to the east by TALEGAON AMBI ROAD and to the west by SURVEY NO 53. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park18 km
Baner–Balewadi belt23 km
Pune Int'l Airport (Lohegaon)31 km
Pune Junction / city centre32 km
Kharadi / EON IT Park35 km
Magarpatta / Hadapsar IT37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kohinoor Associates is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Kohinoor Associates

Other RERA-registered projects in Talegaon Dabhade

Hillcrest
possession by Oct 2026 · Swapnashilp Buildcon
Greendale ENA
possession by Dec 2026 · M/s. Karpe Construction Company
Indraprasth
possession by Dec 2026 · J V Buildcon
Krishna Mahel
Deregistered by MahaRERA · possession by Dec 2026 · Mahesh Developers Ltd
Panoramaa
possession by Dec 2026 · Kakade Properties
SAI Ganesh
possession by Dec 2026 · Aditya Developers

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Kohinoor Business Tower
possession by Dec 2028 · Rising Associates
Kohinoor Business Tower-Baner
possession by Oct 2029 · Revoluxe Estates LLP
Kohinoor Central Park - Phase 1
possession by Dec 2028 · Intofinity Promoters Private Limited
Kohinoor Central Park - Phase II
possession by Oct 2029 · Intofinity Promoters Private Limited
Kohinoor Famville
possession by Dec 2028 · Yellowstone Skyscrapers LLP
Kohinoor Grandeur
declared completion Mar 2024 · Rising Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026