MahaRERA Property Intelligence · Pune

Krupa

P52100016231 · Sanas Nagar · promoter Pam Reality Pvt

Certificate SignedDue 30 May 2022

Delivery & Registration

MahaRERA registrationP52100016231
Registered on25 Apr 2018
Promoter-declared completion30 May 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
A1G+1031 May 2021
B1G+1031 May 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Sanas Nagar, Sanas Nagar, Haveli, Pune, 411024. Per the filed land record, the plot is bounded to the north by G No 21, to the south by G No 29, to the east by G No 22 24 25 and to the west by panand rasta. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt6 km
Pune Junction / city centre9 km
Hinjewadi Rajiv Gandhi IT Park11 km
Magarpatta / Hadapsar IT14 km
Pune Int'l Airport (Lohegaon)16 km
Kharadi / EON IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kirkatwadi

Malhar Heights
possession by Sep 2026 · Ganesh Shrirang Khengre
Vasundhara Phase I
possession by Dec 2026 · Walsis Properties
Shri Samartha Vihar
possession by Dec 2026 · Shri Samarth Developers
Skyi Star City Phase IV
possession by Mar 2027 · Skyi Property Ventures LLP
Chaitrangan Phase II
possession by May 2027 · Dedge Housing Development LLP
Skyi Star City Phase VII
possession by May 2027 · Skyi Property Ventures LLP

Other RERA-registered projects in Pune

Krupa
possession by Dec 2026 · PAM Realty PVT LTD
Krupa
possession by Dec 2028 · Kamat Gandhi Venture
Krupa Apartment
declared completion Aug 2023 · Ramkamal Construction
Krupachhatra Complex
declared completion Apr 2021 · Mehta Builders
Krupasindhu Classic
possession by Jun 2027 · Angaraj Mahadev Gaikwad
Krupasindhu Corner
declared completion Jan 2020 · Dhanlaxmi Builders And Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026