MahaRERA Property Intelligence · Pune

LAXMI PURAM

P52100028932 · KHADAKWASLA · promoter Vipul Construction

Certificate SignedDue 30 Sep 2027

Delivery & Registration

MahaRERA registrationP52100028932
Registered on15 Apr 2021
Promoter-declared completion30 Sep 2027
Current statusCertificate Signed
Against today14 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vipul Construction is the promoter of record on 14 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~38.8% of the estimated project cost incurred as of the last certificate (₹1.54 Cr spent against a ₹3.96 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 40 homes filed with MahaRERA, 4 are sold/booked and 36 remain available (~10% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹98.50 Lakh in agreement value so far. Of that, ₹93.34 Lakh (~95%) is already collected, ₹5.16 Lakh receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1A-101380 sqft (35.26 sqm)₹16.79 Lakh
Floor 1A-102383 sqft (35.62 sqm)₹16.96 Lakh
Floor 1A-103348 sqft (32.29 sqm)₹15.37 Lakh
Floor 1A-104359 sqft (33.38 sqm)₹15.89 Lakh
Floor 1B- 103372 sqft (34.58 sqm)₹16.46 Lakh
Floor 1B-101366 sqft (34.01 sqm)₹16.19 Lakh
Floor 1B-102370 sqft (34.35 sqm)₹16.35 Lakh
Floor 1B-104372 sqft (34.58 sqm)₹16.46 Lakh
Floor 1B-105578 sqft (53.73 sqm)₹25.58 Lakh
Floor 1B-106387 sqft (35.91 sqm)₹17.10 Lakh
Floor 2A-204359 sqft (33.37 sqm)₹15.89 Lakh
Floor 2B-201366 sqft (34.01 sqm)₹16.19 Lakh
Floor 2B-202370 sqft (34.35 sqm)₹16.35 Lakh
Floor 2B-203372 sqft (34.58 sqm)₹16.46 Lakh
Floor 2B-204372 sqft (34.58 sqm)₹16.46 Lakh
Floor 2B-205578 sqft (53.73 sqm)₹25.58 Lakh
Floor 2B-206387 sqft (35.91 sqm)₹17.10 Lakh
Floor 3A-301380 sqft (35.26 sqm)₹16.79 Lakh
Floor 3A-303348 sqft (32.29 sqm)₹15.37 Lakh
Floor 3A-304359 sqft (33.38 sqm)₹15.89 Lakh
Floor 3B-301366 sqft (34.01 sqm)₹16.19 Lakh
Floor 3B-302370 sqft (34.35 sqm)₹16.35 Lakh
Floor 3B-303372 sqft (34.58 sqm)₹16.46 Lakh
Floor 3B-304372 sqft (34.58 sqm)₹16.46 Lakh
Floor 3B-305578 sqft (53.73 sqm)₹25.58 Lakh
Floor 3B-306387 sqft (35.91 sqm)₹17.10 Lakh
Floor 4A-401380 sqft (35.26 sqm)₹16.79 Lakh
Floor 4A-402383 sqft (35.62 sqm)₹16.96 Lakh
Floor 4A-403348 sqft (32.29 sqm)₹15.37 Lakh
Floor 4A-404359 sqft (33.38 sqm)₹15.89 Lakh
Floor 4B-401366 sqft (34.01 sqm)₹16.19 Lakh
Floor 4B-402370 sqft (34.35 sqm)₹16.35 Lakh
Floor 4B-403372 sqft (34.58 sqm)₹16.46 Lakh
Floor 4B-404372 sqft (34.58 sqm)₹16.46 Lakh
Floor 4B-405578 sqft (53.73 sqm)₹25.58 Lakh
Floor 4B-406387 sqft (35.91 sqm)₹17.10 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 40 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
LAXMI PURAM A WING1G+416-
LAXMI PURAM B WING1G+424-

Unit mix on the filing: 40 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
19 Feb 202530 Sep 2027We have made the decision to revise our plan to ensure a more comprehensive and effective implementation. The revised plan necessitates additional time to ensure all components are

Location, Land & Connectivity

Located at KHADAKWASLA, KHADAKWASLA, Haveli, Pune, 411024. Per the filed land record, the plot is bounded to the north by BY PROPERTY OF MR LAXMAN RANDHIR, to the south by BY PUNE SINHAGAD ROAD, to the east by BY PROPERTY OF MR SANTOSH KAMBLE and to the west by BY GOVERNMENT PROPERTY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Baner–Balewadi belt13 km
Pune Junction / city centre14 km
Hinjewadi Rajiv Gandhi IT Park17 km
Magarpatta / Hadapsar IT18 km
Kharadi / EON IT Park21 km
Pune Int'l Airport (Lohegaon)22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other flagged projects by Not Available

Other RERA-registered projects in Kirkatwadi

Malhar Heights
possession by Sep 2026 · Ganesh Shrirang Khengre
Vasundhara Phase I
possession by Dec 2026 · Walsis Properties
Shri Samartha Vihar
possession by Dec 2026 · Shri Samarth Developers
Skyi Star City Phase IV
possession by Mar 2027 · Skyi Property Ventures LLP
Chaitrangan Phase II
possession by May 2027 · Dedge Housing Development LLP
Skyi Star City Phase VII
possession by May 2027 · Skyi Property Ventures LLP

Other RERA-registered projects in Pune

Laxmi Residency
declared completion Sep 2023 · Nanda Manjule
Laxmi Shantiban
declared completion Oct 2019 · Laxmi Roperties
Laxmi Shrushti
possession by Mar 2028 · Shrushti Developers
Laxmi Vihar A And B Building
possession by Dec 2027 · V S Kalbhor AND Company
Laxmi Vihar C Building
declared completion Sep 2025 · V S Kalbhor AND Company
Laxmi Villa
declared completion Jun 2022 · Umesh Manoharrao Wakode

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026