Pune/Project record

MahaRERA · the public record

24 Aanand P1

Ramling Road · BJ Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

13units filed as unsoldInventory · 12 September 2026
31 Oct 2028declared completionMahaRERA registration · read 02 Jul 2026
41registered unitsMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PC1261012600091

Delivery and registration

When is the project declared for completion?

24 Aanand P1 is registered with MahaRERA as PC1261012600091 and the promoter has declared completion for 31 Oct 2028.

31 Oct 2028

declared completion

25months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPC1261012600091
Registered on15 Apr 2026
Promoter-declared completion31 Oct 2028
Current statusCertificate Signed
Against today25 months to the declared date

Sales

How much has actually been sold?

In 24 Aanand P1, 0 of 41 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 41 remain available.

0%sold

0 of 41 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 28 homes carry one, and 13 of the 41 are recorded unsold. Since we started watching this ledger, 28 homes have moved out of the unsold list, most recently on 04 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
S-101343 sqftRs 17.74 lakh to Rs 19.24 lakh2 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In 24 Aanand P1, 11 of the 13 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 12 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15 and 41 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
24 Aanand1G+1541-

Unit mix on the filing: 41 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ramling Road, City Survey No. 1920/1, Shirur, Pune, 412210. Per the filed land record, the plot is bounded to the north by 24.00 m Road, to the south by 9.00 m Road, to the east by 18.00 m Road and to the west by CTS No. 1920/4. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~55 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park55 km
Pune Int'l Airport (Lohegaon)55 km
Magarpatta / Hadapsar IT59 km
Pune Junction / city centre62 km
Baner–Balewadi belt70 km
Hinjewadi Rajiv Gandhi IT Park72 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Not Available is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Not Available

Other RERA-registered projects in Shirur

1 Sadabaug Phase-II
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-III
possession by Sep 2026 · Lalita Dharamchand Phulfagar
Babji Market
possession by Sep 2026 · Pyramid Constructions
Rayat Residency
possession by Sep 2026 · Soham Constructions AND Developers
Kuber Park Phase-I
Past its declared completion date · possession by Oct 2026 · Bhujbal Buildcon
Sunshine Residency
possession by Dec 2026 · Sunshine Construction AND Developers

Other RERA-registered projects in Pune

24 Aanand P2
possession by Apr 2030 · Not Available
24 Carat
declared completion Dec 2020 · ABC AND Mittal Realty
24 Casa Sanjivani
possession by Oct 2027 · Girish Bhaidas Patil
24 Elements
declared completion May 2026 · S.p. Builders AND Developers
24 Hill Crest
possession by Oct 2029 · B G Developers
24 Kalpavriksha
possession by Sep 2028 · Sathe Gandhi Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026