MahaRERA Property Intelligence · Pune

Kuber Park Phase-I

P52100032227 · Shirur · promoter Bhujbal Buildcon

Certificate SignedDue 31 Oct 2026

Delivery & Registration

MahaRERA registrationP52100032227
Registered on15 Dec 2021
Promoter-declared completion31 Oct 2026
Current statusCertificate Signed
Against today3 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Bhujbal Buildcon is the promoter of record on 12 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~59.3% of the estimated project cost incurred as of the last certificate (₹2.87 Cr spent against a ₹4.83 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 28 homes filed with MahaRERA, 11 are sold/booked and 17 remain available (~39% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹3.64 Cr in agreement value so far. Of that, ₹2.85 Cr (~78%) is already collected, ₹79.14 Lakh receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 11 registered agreements, the effective carpet rate is ₹5,419/sqft (typical range ₹5,071–₹6,194) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101452 sqft (42 sqm)₹26.00 Lakh
Floor 1104646 sqft (60 sqm)₹28.00 Lakh
Floor 2203452 sqft (42 sqm)₹26.00 Lakh
Floor 3301452 sqft (42 sqm)₹26.00 Lakh
Floor 3303636 sqft (59.09 sqm)₹28.00 Lakh
Floor 4402646 sqft (60 sqm)₹28.00 Lakh
Floor 4403636 sqft (59.09 sqm)₹28.00 Lakh
Floor 5501452 sqft (42 sqm)₹26.00 Lakh
Floor 5503635 sqft (59 sqm)₹28.00 Lakh
Floor 5504646 sqft (60 sqm)₹28.00 Lakh
Floor 6601452 sqft (42 sqm)₹26.00 Lakh
Floor 6603636 sqft (59.09 sqm)₹28.00 Lakh
Floor 6604646 sqft (60 sqm)₹28.00 Lakh
Floor 7701452 sqft (42 sqm)₹26.00 Lakh
Floor 7702646 sqft (60 sqm)₹28.00 Lakh
Floor 7703636 sqft (59.09 sqm)₹28.00 Lakh
Floor 7704646 sqft (60 sqm)₹28.00 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 28 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
B Wing1G+52831 Dec 2023

Unit mix on the filing: 28 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202331 Oct 2026We received the Occupancy Certificate (OC) on 04/04/2024. Accordingly, we have applied for an extension of the project registration.We kindly request you to accept and approve our

Location, Land & Connectivity

Located at Shirur, Vitthalnagar, Shirur, Pune, 412210. Per the filed land record, the plot is bounded to the north by Trimurti Vision Phase-II Building, to the south by Suryakant Bhujbal Land, to the east by Survey No 298 C and to the west by 30 FT Internal Road and Developers Land. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~56 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park56 km
Pune Int'l Airport (Lohegaon)56 km
Magarpatta / Hadapsar IT59 km
Pune Junction / city centre63 km
Baner–Balewadi belt70 km
Hinjewadi Rajiv Gandhi IT Park73 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shirur

Advik Paradise
possession by Aug 2026 · NG Developers
1 Sadabaug Phase-I
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-II
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-III
possession by Sep 2026 · Lalita Dharamchand Phulfagar
Babji Market
possession by Sep 2026 · Pyramid Constructions
Rayat Residency
possession by Sep 2026 · Soham Constructions AND Developers

Other RERA-registered projects in Pune

Kuber Properties Kuber Antonia B
possession by Apr 2027 · Not Available
Kudale Residency
declared completion Dec 2023 · M/S Ideal Promoters AND Developers
Kul Utsav Ph 1 C Building
declared completion Oct 2020 · Kumar Builders
Kul Utsav Ph I E Building
declared completion Nov 2020 · Kumar Builders
Kul Utsav Phase I - Building D
declared completion Oct 2020 · Kumar Builders
KUL Utsav Phase I -Building F
declared completion Dec 2019 · Kumar Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026