KRUSHNA KUNJ
CHIKHALI · TUSHAR BALKRISHNA NEWALE
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2023
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100022528
Delivery and registration
When is the project declared for completion?
KRUSHNA KUNJ is registered with MahaRERA as P52100022528 and the promoter has declared completion for 30 Jun 2023.
30 Jun 2023
declared completion
39months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100022528 |
| Registered on | 30 Sep 2019 |
| Promoter-declared completion | 30 Jun 2023 |
| Current status | Certificate Signed |
| Against today | about 39 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KRUSHNA KUNJ record 16 quarterly progress reports since registration.
16quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Tushar Balkrishna Newale is the promoter of record on 44 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
44projects
registered with MahaRERA
10flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for KRUSHNA KUNJ in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| A BUILDING | 1 | G+5 | 30 Dec 2021 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Jun 2023 | Due to covid-19 and unavailability of resources. |
Location, Land & Connectivity
Located at CHIKHALI, CHIKHALI, Mulshi, Pune, 412114. Per the filed land record, the plot is bounded to the north by GAT NO 1591, to the south by 20 FTS ROAD, to the east by GAT NO 1592 and to the west by GAT NO 1592. These are the boundaries as recorded in the filed land record.