Pune/Project record

MahaRERA · the public record

Krushna Kunj

Khed · MNM Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

16units filed as unsoldInventory · 18 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
16registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100047710

Delivery and registration

When is the project declared for completion?

Krushna Kunj is registered with MahaRERA as P52100047710 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100047710
Registered on21 Nov 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Krushna Kunj record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In Krushna Kunj, 0 of 16 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 16 remain available.

0%sold

0 of 16 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Ground/Floor 0A-01950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0A-02950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0A-03950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0A-04950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0A-05950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0A-06950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0A-07950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0A-08950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0B-01950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0B-02950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0B-03950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0B-04950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0B-05950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0B-06950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0B-07950 sqft (88.3 sqm)₹31.27 Lakh
Ground/Floor 0B-08950 sqft (88.3 sqm)₹31.27 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Krushna Kunj in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 September 2026

What the filings record, home by home

Read from MahaRERA on 18 September 2026

No home in Krushna Kunj carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 16 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 3,291 a sq ft typical, over Rs 3,291 to Rs 3,291.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 16 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 16 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1 and 16 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing A1G+18-
Wing B1G+18-

Unit mix on the filing: 16 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Khed, Nighoje, Pune City, Pune, 410501. Per the filed land record, the plot is bounded to the north by Property of partners of MNM Developers, to the south by Property of shri Kalidas Kanhurkar, to the east by Gat No 339 plot No 1 and to the west by Part land of serial No 1555A and Moi. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park14 km
Baner–Balewadi belt15 km
Pune Int'l Airport (Lohegaon)16 km
Pune Junction / city centre18 km
Kharadi / EON IT Park20 km
Magarpatta / Hadapsar IT22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chakan

Vallabh Heights
possession by Sep 2026 · G R Developers
Shree Samarth Shrushti
possession by Sep 2026 · Jagdamba Developers
Swapnapurti Heights
Not filing quarterly progress reports · possession by Oct 2026 · B R Developers
Richmond
possession by Oct 2026 · Coral Shubh Builders
Mungase Towers
possession by Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

Major developers building in Chakan

Other RERA-registered projects in Pune

Krushna Kunj Vihar
possession by Dec 2028 · Raj Rajeshwar Developers
Krushna Paradise
declared completion Oct 2025 · Mehta Builders
Krushnagandha
declared completion Jul 2022 · Devidas Bachchu Dangat
Krushnai Homes
possession by Dec 2027 · Sukhkarta Construction AND Developers
Krushnai Impirio
declared completion Jan 2020 · Krushnai Buildcon
Krushnai Plaza
declared completion Sep 2022 · RVR Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026