30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100022671

Delivery and registration

When is the project declared for completion?

KRUSHNAKUNJ is registered with MahaRERA as P52100022671 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100022671
Registered on12 Oct 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KRUSHNAKUNJ record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Gurudatta Properties is the promoter of record on 24 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

24projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KRUSHNAKUNJ in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
B1G+531 Dec 2022
A1G+331 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BRAHMAN ALI, BRAHMAN ALI ROAD, Khed, Pune, 410505. Per the filed land record, the plot is bounded to the north by SURVEY NO 1309 1310 1311 1313, to the south by SURVEY NO 1330 1331, to the east by ROAD and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rajgurunagar

Kohinoor Heights
possession by Oct 2026 · Abbas Ayub Ansari
Shree Paradise
possession by Oct 2026 · Sunita Ashutosh Gosavi
Rajashri Apartments
possession by Oct 2026 · Omkar Sanjay Thigale
Classic Amrut
possession by Oct 2026 · Classic Infra
Mahalaxmi Heights
possession by Dec 2026 · Mahalaxmi Developers
Aryaa Dream Town
possession by Dec 2026 · Vini Builders AND Developers

Major developers building in Rajgurunagar

Other RERA-registered projects in Pune

Krushnakunj
declared completion Dec 2023 · Ananda Raghunath Solat
Krushnakunj
declared completion Dec 2025 · Not Available
Krushnarang Villa
declared completion Dec 2022 · Amit Tukaram Zapke
Krutarth
possession by Dec 2029 · Majestique Duropolis Pvt Ltd
Krutika Residency
declared completion Sep 2025 · Chandrakant Baban Sawant
Krutika Residency-Wing-A
possession by Dec 2028 · Parth Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026