MahaRERA Property Intelligence · Pune

LAKE SHORE RESIDENCES

P52100018088 · DHANORI · promoter Aaiji Group

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52100018088
Registered on10 Oct 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aaiji Group is the promoter of record on 12 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
BUILDING G1G+1231 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at DHANORI, DHANORI, Pune City, Pune, 411015. Per the filed land record, the plot is bounded to the north by NALA, to the south by SR NO 39 PART, to the east by BY ROAD and to the west by NALA GARDEN. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhanori

Gada Elina
possession by Jul 2026 · Kubix Realties LLP
Belmont Aster
possession by Aug 2026 · Prakash Ganpatrao Kshirsagar
Belmont Jasmine
possession by Aug 2026 · Uttam Nivrutti Dimbale
Murli Manohar Heights
possession by Sep 2026 · Padmanabh Associates
Yash Grecia- E Wing
possession by Sep 2026 · Akshay Enterprises
Aaiji Crystal Phase I
possession by Oct 2026 · Aaiji Developers

Major developers building in Dhanori

Other RERA-registered projects in Pune

Lake Tierra
possession by Dec 2026 · Anand Constructions
Lake Tower
declared completion Apr 2026 · Tushar Pramod Nagarkar
Lake Town D-6, Wing - A And B
declared completion Mar 2026 · Venkatesh Associates
Lake View 6,7,8,9 - Lcl0007
declared completion Dec 2021 · Lavasa Corporation Ltd
Lake Villas
declared completion Dec 2024 · Siddhivinayak Marketing AND Developers
Lake Vista
declared completion Jun 2024 · Lake Vista Propertis LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026