MahaRERA Property Intelligence · Pune

LANDMARK TRADE CENTRE

P52100027925 · DADACHI VASTI LOHEGAON · promoter Nilesh Purushottam Tapkir

Certificate SignedDue 12 May 2025

Delivery & Registration

MahaRERA registrationP52100027925
Registered on15 Jan 2021
Promoter-declared completion12 May 2025
Current statusCertificate Signed
Against todayabout 14 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nilesh Purushottam Tapkir is the promoter of record on 36 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
LANDMARK TRADE CENTRE1G+712 Nov 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at DADACHI VASTI LOHEGAON, LOHEGAON WAGHOLI, Haveli, Pune, 411047. Per the filed land record, the plot is bounded to the north by 22, to the south by 21, to the east by 45 and to the west by 49. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lohegaon

Nivasa Enchante Phase 2
possession by Aug 2026 · Nivasa Associates
Aayush Exotica
possession by Sep 2026 · Aayush Properties
Chandan Heritage
possession by Sep 2026 · City Developers
Youthika
possession by Oct 2026 · Krushnarang Group
Easterlia
possession by Dec 2026 · Spacemint Realty LLP
Pankaj Aasmaan Phase V
possession by Dec 2026 · Pankaj Developers

Major developers building in Lohegaon

Other RERA-registered projects in Pune

Landmarkk Comerciaa
possession by Dec 2027 · Landmarkk Townships
Landmarkk Luxuria
possession by Dec 2027 · Landmarkk Townships
Landson Shine
possession by Dec 2026 · Landson Properties
Lantana Court
declared completion Aug 2019 · Landmark Ventures
Lantana Court A Building
possession by Jul 2027 · Landmark Ventures
Lara Solitaire
possession by Aug 2028 · M/s SC Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026