LAXMI ANGAN

P52100006865 · promoter Sanjay Krishna Patil

Certificate SignedDue 31 Jul 2018

Delivery & Registration

MahaRERA registrationP52100006865
Registered on16 Aug 2017
Promoter-declared completion31 Jul 2018
Current statusCertificate Signed
Against todayabout 96 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
LAXMI ANGAN1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Mulshi, Pune, 411019. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by CTS NO 7631 and to the west by CTS NO 7629. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~87 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park87 km
Baner–Balewadi belt93 km
Pune Junction / city centre103 km
Pune Int'l Airport (Lohegaon)103 km
Kharadi / EON IT Park107 km
Magarpatta / Hadapsar IT108 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chinchwad

THE Central Park Phase -I
possession by Dec 2026 · R Retail Ventures Private Limited
Manorama Heights
possession by Dec 2026 · Manali Bridgecast LLP
Palaash Aayush
possession by Jan 2027 · S P B Infra
THE Central Park Phase - II
possession by Jun 2027 · R Retail Ventures Private Limited
THE Central Park Phase - III
possession by Jun 2027 · R Retail Ventures Private Limited
Palaash Aayush Phase 2
possession by Dec 2027 · S P B Infra

Major developers building in Chinchwad

Other RERA-registered projects in Pune

Laxmi Angan
declared completion May 2024 · Ashish Builders
Laxmi Avenue
declared completion Jun 2024 · Laxman Saibana Mehetre
Laxmi Balaji Apartment
possession by Dec 2027 · Suresh Balliaha Nagraj
Laxmi Bappa
possession by May 2027 · Stone Shelters LLP
Laxmi Bhakti
declared completion Mar 2019 · L S Mehetre & Sukhwani Shelters
Laxmi Bliss
declared completion Dec 2025 · Shree Mahalaxmi Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026