MahaRERA Property Intelligence · Pune

MADHURA BUILDERS AND DEVELOPERS BLDG -A

P52100013790 · promoter Shekhar Narayan More

Certificate SignedDue 30 Jun 2021

Delivery & Registration

MahaRERA registrationP52100013790
Registered on25 Oct 2017
Promoter-declared completion30 Jun 2021
Current statusCertificate Signed
Against todayabout 61 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shekhar Narayan More is the promoter of record on 49 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
VRUNDAVAN VILA1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Khed, Pune, 410505. Per the filed land record, the plot is bounded to the north by WAFGAON ROD, to the south by RAKSHEWADI ROAD, to the east by OPEN SPACE and to the west by RCC BUNGLOW. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~89 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park89 km
Baner–Balewadi belt94 km
Pune Junction / city centre105 km
Pune Int'l Airport (Lohegaon)107 km
Kharadi / EON IT Park110 km
Magarpatta / Hadapsar IT110 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rajgurunagar

7 Sagar Plaza
possession by Aug 2026 · Sagar Kaluram Patole
Shree Paradise
possession by Oct 2026 · Sunita Ashutosh Gosavi
Rajashri Apartments
possession by Oct 2026 · Omkar Sanjay Thigale
Classic Amrut
possession by Oct 2026 · Classic Infra
Mahalaxmi Heights
possession by Dec 2026 · Mahalaxmi Developers
Aryaa Dream Town
possession by Dec 2026 · Vini Builders AND Developers

Other RERA-registered projects in Pune

Madhurangan Apartment
declared completion Sep 2020 · Shri Yogesh Prabhakar Dhole
Madhusagar
declared completion Jun 2026 · Siddhashila Ventures LLP
Madhushila Heritage
declared completion Dec 2024 · Shree Sai Construction
Madhushree
declared completion May 2026 · KPL Build CON LLP
Madhusmruti
possession by May 2028 · NDG Developers LLP
Madhusparsha
declared completion Dec 2022 · Madhukar Namdev Mohite

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026