MAHA LAXMI RESIDENCY

Pune · SHRI GOVIND ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100010685

Delivery and registration

When is the project declared for completion?

MAHA LAXMI RESIDENCY is registered with MahaRERA as P52100010685 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100010685
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAHA LAXMI RESIDENCY record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shri Govind Associates is the promoter of record on 145 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

145projects

registered with MahaRERA

23flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAHA LAXMI RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
MAHA LAXMI RESIDENCY1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Haveli, Pune, 411019. Per the filed land record, the plot is bounded to the north by GAT NO 741 P, to the south by ROAD 9M WIDE ROAD, to the east by GAT NO 752 P and to the west by GAT NO 752 P. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~91 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park91 km
Baner–Balewadi belt96 km
Pune Junction / city centre106 km
Pune Int'l Airport (Lohegaon)106 km
Kharadi / EON IT Park110 km
Magarpatta / Hadapsar IT111 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shri Govind Associates is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shri Govind Associates

Shri Govind Associates
FlaggedPune

Other RERA-registered projects in Chinchwad

THE Central Park Phase -I
possession by Dec 2026 · R Retail Ventures Private Limited
Manorama Heights
possession by Dec 2026 · Manali Bridgecast LLP
Palaash Aayush
possession by Jan 2027 · S P B Infra
THE Central Park Phase - II
possession by Jun 2027 · R Retail Ventures Private Limited
THE Central Park Phase - III
possession by Jun 2027 · R Retail Ventures Private Limited
Palaash Aayush Phase 2
possession by Dec 2027 · S P B Infra

Major developers building in Chinchwad

Other RERA-registered projects in Pune

Maha Laxmi Residency
declared completion Feb 2022 · Shri Govind Associates
Maha Trade Market PH- 1
possession by Jun 2027 · Jairaj Realty LLP
Maha Trade Market PH- 2
possession by Jun 2027 · Jairaj Realty LLP
Mahadeo Dreams
declared completion May 2026 · Shree Ganesh Associates
Mahadev Heights
declared completion Mar 2022 · Nilesh Kisanrao Jawalkar
Mahadev Park
declared completion Mar 2023 · Omkar Developers & Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026