Pune/Project record

MahaRERA · the public record

Malhar Vishwa

Jejuri · Ovaks Builders and Promoters

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100023790

Delivery and registration

When is the project declared for completion?

Malhar Vishwa is registered with MahaRERA as P52100023790 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100023790
Registered on06 Jan 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Malhar Vishwa record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Malhar Vishwa in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Malhar Vishwa1G+431 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Jejuri, Jejuri to Morgaon road, Purandhar, Pune, 412303. Per the filed land record, the plot is bounded to the north by Compound wall, to the south by 18 M DP road, to the east by S no 1477 and 1478 and to the west by S No 1501 and 4. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jejuri

Savali Plaza
possession by Dec 2026 · Savali Associates
Krishnachhaya
Not filing quarterly progress reports · possession by Dec 2026 · Shri Dattaprabhu Construcction
Malhar Resisdency
Not filing quarterly progress reports · possession by Dec 2026 · JAI Malhar Promoter AND Developers
Purandar Plaza
possession by Dec 2026 · Shri Hari Om Constructions
JAY Shankar Complex
possession by May 2027 · Arun Shankar Joshi
Mhalsakant Sakharam Peshave
possession by Jun 2027 · Mhalasakant Sakharam Peshave

Other RERA-registered projects in Pune

Malhargad View
possession by Oct 2027 · Harinima Builders
Mamurdi Mhada North
possession by Mar 2027 · Godrej Skyline Developers Limited
Manali Falcon
possession by Mar 2029 · Prasannam Realtors
Manas
declared completion Jun 2022 · Niwas Enterprises
Manas
possession by Jun 2029 · Skyline Enterprises
Manas Residency
possession by Dec 2026 · Oorjitaa Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026