MahaRERA · the public record
Manorath
Bhangarwadi · Samarth Realty
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100028793
Delivery and registration
When is the project declared for completion?
Manorath is registered with MahaRERA as P52100028793 and the promoter has declared completion for 30 Jun 2026.
30 Jun 2026
declared completion
3months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100028793 |
| Registered on | 30 Mar 2021 |
| Promoter-declared completion | 30 Jun 2026 |
| Current status | Certificate Signed |
| Against today | about 3 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Manorath record 22 quarterly progress reports since registration.
22quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.
Construction
How much construction cost has been reported?
In Manorath, ₹6.60 Cr of a declared ₹7.00 Cr estimated project cost is reported as incurred, about 94.3%, as at the last certified filing with MahaRERA.
94.3%
₹6.60 Cr
of ₹7.00 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Manorath, 1 of 42 homes filed with MahaRERA are recorded as sold or booked, about 2%, and 41 remain available.
2%sold
1 of 42 homes
₹62.58 Lakh
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹52.65 Lakh (about 84%) is recorded as collected and ₹9.93 Lakh as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Manorath in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 17 September 2026
What the filings record, home by home
Read from MahaRERA on 17 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 1 homes carry one, and 41 of the 42 are recorded unsold.
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3 and 42 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Wing A and Wing B | 1 | G+3 | 42 | - |
Unit mix on the filing: 42 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 28 Dec 2025 | We, hereby apply for extension u/s 7(3) of the registered project bearing vide no. P52100028793 up to 28/12/2025.As prescribed under circular no 07/2019 dated 8 Feb 2019, the conse |
| 28 Dec 2025 | 30 Jun 2026 | We hereby request an extension of the project timeline under RERA due to unforeseen delays arising from multiple factors beyond our control. As the project is located in Lonavala, |
Location, Land & Connectivity
Located at Bhangarwadi, Bhangarwadi - Village Nagargaon, Pune City, Pune, 410401. Per the filed land record, the plot is bounded to the north by CTS No 182, to the south by CTS No 184 186 C 185 186 D 186 E, to the east by CTS No 186 F and to the west by CTS No 186 A. These are the boundaries as recorded in the filed land record.