Pune/Project record

MahaRERA · the public record

Mata Ramai Magaswargiya Sah GGraharachana Sanstha Maryadit

Pune · Mata Ramai Magaswargiya Sah Graharachana Sanstha Maryadit

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Aug 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Aug 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100011009

Delivery and registration

When is the project declared for completion?

Mata Ramai Magaswargiya Sah GGraharachana Sanstha Maryadit is registered with MahaRERA as P52100011009 and the promoter has declared completion for 01 Aug 2022.

01 Aug 2022

declared completion

49months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100011009
Registered on31 Aug 2017
Promoter-declared completion01 Aug 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Mata Ramai Magaswargiya Sah GGraharachana Sanstha Maryadit record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Mata Ramai Magaswargiya Sah GGraharachana Sanstha Maryadit in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
B Type1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered01 Feb 2022The members to whom the flats are sold are not able to pay the balance dues in the stipulated time period. Hence, the time period for the project needs to be extended so that the f

Location, Land & Connectivity

Located at Haveli, Pune, 411048. Per the filed land record, the plot is bounded to the north by Adj Road, to the south by Plot of Sr No 5, to the east by D P Road and to the west by Plot of Sr No 5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~83 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park83 km
Baner–Balewadi belt88 km
Pune Int'l Airport (Lohegaon)97 km
Pune Junction / city centre98 km
Kharadi / EON IT Park101 km
Magarpatta / Hadapsar IT103 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Khurd

Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kapital
possession by Dec 2026 · Ostwal Realty
Akshardham Phase 2
possession by Dec 2026 · Shreyan Ventures
Clover Highlands
possession by Dec 2026 · Clover Developers Pvt Ltd
Hagawane Landmark
Not filing quarterly progress reports · possession by Dec 2026 · Santosh Subhash Hagawane

Major developers building in Kondhwa Khurd

Other RERA-registered projects in Pune

Mathura Towers
declared completion Mar 2026 · Shri Mathura Constructions
Mathura Vaibhav
possession by Dec 2028 · Lande Patil Associates
Mathurakunj
possession by Dec 2028 · Manasara Vaastu Private Limited
Matoshree Aradhyam
possession by Dec 2027 · Matoshri Properties
Matoshree Pride
declared completion Aug 2026 · Devidas Suresh Bhat
Matoshree Residency
declared completion Dec 2025 · Krushnai Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026