mexico

gunavdi · ARIF SHABBIR SHAIKH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017266

Delivery and registration

When is the project declared for completion?

mexico is registered with MahaRERA as P52100017266 and the promoter has declared completion for 30 Jun 2021.

30 Jun 2021

declared completion

63months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017266
Registered on26 Jul 2018
Promoter-declared completion30 Jun 2021
Current statusCertificate Signed
Against todayabout 63 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for mexico record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Arif Shabbir Shaikh is the promoter of record on 13 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for mexico in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
mexico1G+331 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021Because of corona crisis, the real estate market in baramati is in the worst condition and as a company we are financially very unstable due to this market scenario. We request for

Location, Land & Connectivity

Located at gunavdi, gunavdi road, Pune City, Pune, 413102. Per the filed land record, the plot is bounded to the north by adjacent plot, to the south by 12m wide road, to the east by open space and to the west by 9m wide road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~80 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT80 km
Kharadi / EON IT Park81 km
Pune Int'l Airport (Lohegaon)85 km
Pune Junction / city centre85 km
Baner–Balewadi belt96 km
Hinjewadi Rajiv Gandhi IT Park101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baramati

Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon
Adarsh Residency
possession by Oct 2026 · Shivshree Developers
Dream City -A Building
possession by Oct 2026 · Tanaji Sadashiv Pansare
Tanai Heights
possession by Nov 2026 · Surekha Vishnu Kumbhar
Tanai G
possession by Nov 2026 · Surekha Vishnu Kumbhar
Shrivishwa Heights
possession by Dec 2026 · Shrivishwa Developers

Other RERA-registered projects in Pune

Mezon Landmark
possession by Dec 2027 · Mezon Landwork
MGP Siddhiksha
possession by Dec 2026 · MGP Developers
MGP Suanand
declared completion Dec 2024 · MGP Developers
Mhada-TCG Gardenia
possession by Dec 2027 · THE Construction & Development CO
Mhalsakant Sakharam Peshave
possession by Jun 2027 · Mhalasakant Sakharam Peshave
Miami-A1-A2-A3-B2
possession by Dec 2029 · Pride Builders LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.